up
Budget Year / Version:  
anchor
anchor
anchor

Description

Beginning in 2025, MCPS hired a third party contractor to conduct facility assessments which led to a data set known as a Facility Condition Index (FCI). These assessments will eventually be performed at all facilities, but an initial batch of approximately 50 schools were identified. The initial batch of schools had been included in recent CIPs, scored high on the Maryland Condition Index (MDCI), or had not received a major capital project for over 50 years. Along with the FCI, other relevant data sets were incorporated into a new CIP prioritization framework that led to the requested FY 2027 Major Capital Projects.

The first four elementary schools prioritized under this newly established approach include Burning Tree, Cold Spring, Piney Branch, and Highland View, previously identified as an addition project. All of these projects were requested to begin planning in FY 2028 with completion dates of August 2031. Due to fiscal constraints, in the adopted FY2027-2032 CIP, the County Council approved these projects with planning starting in FY31 and anticipated completion dates of August 2034.

Subsequently, Damascus, Twinbrook, and Whetstone elementary schools ranked lower in the prioritization process, therefore, the Board is requesting previously appropriated funds to be reallocated to other projects.
anchor

Phase

Status

Active
anchor
Budget Snapshot
$460.85M Total
Expenditures/Funding
$33.46M 6 Year Total
Expenditures/Funding
anchor

Fiscal Note

FY21 supplemental in G.O. Bonds for the amount of $5,853,000 to accelerate completion date to 2023 in the South Lake ES. FY22 Supplemental for $16,725,000 in GO Bonds for Burnt Mills ES ($5.2 million); South Lake ES ($2.057 million); Stonegate ES ($3.528 million); and Woodlin ES ($5.940 million).
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore Project Details
Budget Snapshot
$460.85M Total
Expenditures/Funding
$33.46M 6 Year Total
Expenditures/Funding
anchor
Project NumberP652101
Date Last Modified05/20/26
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision38638874944912138800001236790214010
Land00000000000
Site Improvements and Utilities6494219501010853000001085334588
Construction3420281478519891215000001215191973
Other15240681142900000008000
Total Expenditures46084818291259093345600001236721089238571
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds3310815314559093345600001236721089238571
Recordation Tax5211952119000000000
State Aid7764877648000000000
Total Funding Sources46084818291259093345600001236721089238571
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request-8409
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate288914
Cumulative Appropriation198073
Expenditure / Encumbrances0
Unencumbered Balance198073
anchor
Download & Explore Project Details