This project will provide deeply affordable living quarters. The facility will include individual, furnished units with private bathrooms and limited kitchen facilities. The units would be rented at an extremely affordable rate so individuals can end their experience with homelessness and have access to supportive services.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

18 units for 1- or 2-person households
anchor

Estimated Schedule

Initial research and evaluation occurred between FY22-FY24. Further planning and site selection was temporarily on hold pending improved market affordability. Site selection finalized in FY26. Design expected to complete in FY27. Construction expected to complete in FY29.
anchor

Justification

A major obstacle to ending homelessness is the lack of affordable housing. Many individuals that are experiencing homelessness are able to maintain permanent housing when it is affordable and equipped with supportive services. This project will renovate an existing facility to include individual, furnished units with private bathrooms and limited kitchen facilities.
anchor

Fiscal Note

FY22 supplemental in Federal Aid for the amount of $100,000 for planning. FY26 supplemental in Federal Aid for the amount of $7,221,940.
anchor

Coordination

Department of Health and Human Services, Department of Housing and Community Affairs, and Department of General Services
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP602201
Date Last Modified01/10/26
Administering AgencyGeneral Services
CategoryHealth and Human Services
SubCategoryHealth and Human Services
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY27FY28FY29FY30FY31FY32
Program-Other1720--430430430430
NET IMPACT1720--430430430430
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY22
Appropriation FY28 Request0
Last FY's Cost Estimate7322
Cumulative Appropriation7322
Expenditure / Encumbrances5
Unencumbered Balance7317