Description

This project includes planning, which involves community outreach and coordination with elected officials, design, and construction of a submerged channel intake to provide an additional barrier against drinking water contamination (particularly Giardia cysts and Cryptosporidium oocysts), as well as to enhance reliability and reduce treatment costs by drawing water from a location with cleaner, more stable water quality. Both Councils will review the results of the planning work and the updated costs and benefits of the project and must approve continuing the project before design and construction proceed.
anchor

Phase

TBA

Status

Active
anchor
Budget Snapshot
$104.67M Total
Expenditures/Funding
$31.7M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase due to inflation.
anchor

Justification

The project provides for a more reliable supply by eliminating the current problems associated with ice and vegetation blocking the existing bank withdrawal. This project is consistent with the industry's recommended multiple barrier approach.

anchor

Other

The project scope has remained the same. Significant outreach activities occurred as part of the planning phase of this project. The National Environmental Policy Act (NEPA) process was concluded in January 2018 when the National Park Service (NPS) approved the Environmental Assessment and transmitted its record of decision and the Finding of No Significant Impact. Future land costs are included in project W-202.00. Both Councils will review the results of the planning work and the updated costs and benefits of the project and must approve continuing the project before design and construction proceed.

anchor

Coordination

Coordinating Agencies: Maryland Department of Natural Resources; Maryland Department of the Environment; Maryland-National Capital Park & Planning Commission; Montgomery County Department of Environmental Protection; Montgomery County Government; National Park Service; Prince George's County Department of Environmental Resources; Prince George's County Government; U.S. Army Corps of Engineers Coordinating Projects: W - 000073.33 - Potomac WFP Consent Decree Program

Budget Snapshot
$104.67M Total
Expenditures/Funding
$31.7M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP033812
Date Last Modified09/16/24
Administering AgencyW.S.S.C.
CategoryWSSC
SubCategoryWater Bi-County
Planning AreaBi-County
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY24Est FY25Total 6 YearsFY 26FY 27FY 28FY 29FY 30FY 31Beyond 6 Years
Planning, Design and Supervision10663216440051993998008001000100012002900
Land00000000000
Site Improvements and Utilities00000000000
Construction89103103025000000002500064000
Other49010201501214040505013003380
Total Expenditures104667226742031700420840840105010502750070280
FUNDING (000s)
Funding SourceTotalThru FY24Est FY25Total 6 YearsFY 26FY 27FY 28FY 29FY 30FY 31Beyond 6 Years
WSSC Bonds104667226742031700420840840105010502750070280
Total Funding Sources104667226742031700420840840105010502750070280
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request840
Year First AppropriationFY01
Appropriation FY 26 Request420
Last FY's Cost Estimate102215
Cumulative Appropriation19791
Expenditure / Encumbrances0
Unencumbered Balance19791