Description

The project will apply a topcoat to the parking lot to prevent damage from use and the natural climate year-round. The topcoat seals off the parking lot for the future, which will extend the life of the parking lot until further maintenance is needed.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Cost Change

The cost of the topcoat of the parking lot, which was the only part of this project, was higher than originally expected.
anchor

Justification

The Authority is created to construct, improve, equip, furnish, maintain, acquire, operate, and finance projects to be devoted wholly or partially for public uses, good or general welfare. This project supports the long term sustainability of the County's golf course system currently operated by the Revenue Authority.
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP392501
Date Last Modified01/07/26
Administering AgencyRevenue Authority
CategoryRevenue Authority
SubCategoryMiscellaneous Projects (Revenue Authority)
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First Appropriation
Appropriation FY28 Request0
Last FY's Cost Estimate100
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0