up
Budget Year / Version:  
anchor
anchor
anchor

Description

Projections indicate that enrollment will exceed capacity through the six-year planning period. In addition, based on the KFI assessment data, various building systems upgrades/replacements and programmatic requirements are needed for this school. Therefore, the requested FY 2021-2026 CIP includes funding for a Major Capital Project at this school. An FY 2021 appropriation was approved for the architectural planning and design for this project. An FY 2022 appropriation was approved for construction funds for this project. An FY 2022 supplemental appropriation and transfer of funds was approved, in September 2021, for $5.292 million for this project to address construction cost increases. An FY 2022 supplemental appropriation for $5.2 million was approved, in December 2021, to maximize state aid for this project. An FY 2023 appropriation was approved to complete this project. This Major Capital Project is scheduled to be completed August 2023.
project image
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid approved from the County's allocation of the Built To Learn Act school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP652110
Date Last Modified12/19/25
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryCountywide
Planning AreaColesville-White Oak and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY21
Appropriation FY28 Request0
Last FY's Cost Estimate48898
Cumulative Appropriation49158
Expenditure / Encumbrances0
Unencumbered Balance49158