Phase

Planning Stage

Status

Closeout
anchor
Budget Snapshot
$1M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

anchor

Justification

anchor

Coordination

Budget Snapshot
$1M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP602102
Date Last Modified11/19/24
Administering AgencyGeneral Services
CategoryHealth and Human Services
SubCategoryHealth and Human Services
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
$104$896Cost Elements$0$100$200$300$400$500$600$700$800$900$1000Planning Design and SupervisionConstruction
anchor
Total Funding by Source (000s)
100.0%CostElements$-100$0$100$200$300$400$500$600$700$800$900$1000$1100G.O. Bonds
EXPENDITURES (000s)
YearThruRem202520262027202820292030beyond 6years$0$100$200$300$400$500$600$700$800$900Planning Design and SupervisionConstruction
Cost ElementsTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision$104$104$0$0$0$0$0$0$0$0$0
Land$0$0$0$0$0$0$0$0$0$0$0
Site Improvements and Utilities$0$0$0$0$0$0$0$0$0$0$0
Construction$896$890$6$0$0$0$0$0$0$0$0
Other$0$0$0$0$0$0$0$0$0$0$0
Total Expenditures$1,000$994$6$0$0$0$0$0$0$0$0
FUNDING (000s)
YearThruRem202520262027202820292030beyond 6years$0$100$200$300$400$500$600$700$800$900$1000G.O. Bonds
Funding SourceTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds$1,000$994$6$0$0$0$0$0$0$0$0
Total Funding Sources$1,000$994$6$0$0$0$0$0$0$0$0
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request$0
Year First AppropriationFY21
Appropriation FY 26 Request$0
Last FY's Cost Estimate$1,000
Cumulative Appropriation$1,000
Expenditure / Encumbrances$997
Unencumbered Balance$3