Description

This project provides for the replacement of the existing Burnt Hill Road Bridge No. M-0157 over Little Bennett Creek in Clarksburg. The existing bridge, built in 1955, is a single span 19' concrete T-beams with concrete deck structure carrying a 18' clear roadway with no sidewalks. The proposed replacement includes the removal and replacement of the existing bridge abutments and the replacement of the superstructure with prestressed concrete slab beams. The proposed Burnt Hill Road Bridge will be an approximately 34' long simple span bridge carrying a 20' clear roadway. The proposed work includes approximately 550' of stream restoration and 250' of approach roadway work at each end of the bridge. The road and bridge will be completely closed to vehicular traffic during construction and traffic detoured.
anchor

Phase

Final Design Stage

Status

New
anchor
Budget Snapshot
$5.42M Total
Expenditures/Funding
$5.42M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The Average Daily Traffic (ADT) is approximately 825 vehicles. The roadway capacity will not change as a result of this project.
anchor

Estimated Schedule

The design will be completed in FY26. Construction is scheduled for FY28 and will be completed in FY29.
anchor

Justification

The proposed replacement work is necessary to provide a safe roadway condition for the public. The 2022 Bridge Inspection Report indicates that the bridge concrete T-beams are in poor condition with large spalls with exposed and corroded reinforcement steel, large cracks and areas of delamination. The bridge is considered structurally deficient and functionally obsolete. The bridge is currently posted for a 30,000 lb. limit for a single-unit truck and a 30,000 lb. limit for a combination unit truck.
anchor

Fiscal Note

The design cost for this project is funded in the Bridge Design Project (No. 509132). This project does not qualify for Federal aid since existing bridge span is less than 20' in length.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Maryland Department of the Environment, Maryland-National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Utilities, and Bridge Design Project (CIP 509132)
Download & Explore Project Details
Budget Snapshot
$5.42M Total
Expenditures/Funding
$5.42M 6 Year Total
Expenditures/Funding
anchor
Project NumberP502703
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaDamascus and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision00000000000
Land109700109705415560000
Site Improvements and Utilities50000500050000000
Construction38230038230182020030000
Other00000000000
Total Expenditures54200054200286125590000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds54200054200286125590000
Total Funding Sources54200054200286125590000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First Appropriation
Appropriation FY 28 Request5420
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0