Description

This project funds the design and construction of bicycle and pedestrian capital infrastructure in the Wheaton Central Business District (CBD) Bicycle and Pedestrian Priority Area (BiPPA) and identified in the Wheaton Central Business District (CBD) and Vicinity Sector Plan. Recommended improvements will include new sidewalks, separated bikeways, shared-use paths, streetscape improvements, lighting, signal and accessibility upgrades, intersection safety improvements, bike parking, bicyclist and pedestrian wayfinding, and other treatments intended to improve safety and mobility for cyclists and pedestrians. Future projects include intersection safety improvements identified as high priority and near-term in the Wheaton BiPPA Study.
project image
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$11.55M Total
Expenditures/Funding
$8.56M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Final Design for Amherst Avenue Bikeway, a two-way separated bikeway on the west side of Amherst Avenue from Arcola Avenue to Windham Lane, is currently underway and anticipated to be completed in FY24. Construction of Amherst Avenue Bikeway is anticipated to begin in FY25. Design of the Upton Drive Neighborhood Greenway will be completed in FY24, and construction is anticipated to be completed in FY25. Design of the McComas Avenue Neighborhood Greenway will be completed in FY24, and construction is anticipated to be completed in FY25.
anchor

Cost Change

Cost increase due to inflation in FY25-28. Funding for FY29 and FY30 was added.
anchor

Justification

This project will enhance and promote accessibility, safety, mobility and comfort for people walking and biking in the Wheaton CBD. The primary purpose of this project is to build better and safer facilities. In urban areas, walking and bicycling are among the most affordable forms of transportation, providing safe and efficient access to transit. Providing safe, convenient and attractive bicycle and pedestrian access, along with modernizing aging infrastructure is essential to ensure equity for all and provide access to jobs, education, public services and the social network. The Wheaton CBD and Vicinity includes the Wheaton Metro Station and Bus Transfer Center, the Wheaton CBD, town square and adjacent public park and government office building, high-density housing, commercial and retail uses including small businesses and Westfield Wheaton (mall), employment areas, entertainment venues, Wheaton Regional Park, connections to the Sligo Creek Trail, Wheaton Library, Recreation and Community Center, fire and police stations, the Mid-County Regional Services Center, MNCPPC and multiple County agencies, Proyecto Salud Clinic, the Gilchrist Immigration Resource Center, and the Adult Behavioral Health Program. This project supports the ongoing redevelopment of the Wheaton CBD, and will help meet master planned Non-Auto Driver Mode Share (NADMS) goals.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland National Capital Park and Planning Commission (M-NCPPC), Wheaton Urban District Advisory Committee, Maryland DOT State Highway Administration, Washington Metropolitan Area Transit Authority (WMATA), Department of Permitting Services and utilities.
Download & Explore
Budget Snapshot
$11.55M Total
Expenditures/Funding
$8.56M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP502002
Date Last Modified01/11/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision316186854317504316321682132021040
Land692069200000000
Site Improvements and Utilities00000000000
Construction7698918026805264826493673223554640
Other00000000000
Total Expenditures1155195920378555307932815355355575680
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds1099840620378555307932815355355575680
Impact Tax553553000000000
Total Funding Sources1155195920378555307932815355355575680
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Maintenance20--5555
Energy4--1111
NET IMPACT24--6666
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1483
Year First AppropriationFY20
Appropriation FY 26 Request0
Last FY's Cost Estimate9995
Cumulative Appropriation7873
Expenditure / Encumbrances1628
Unencumbered Balance6245