up
Budget Year / Version:  
anchor
anchor
anchor

Description

Project formerly known as Col. E. Brooke Lee MS Addition/ Facility Upgrade. Projections indicate that enrollment at Odessa Shannon Middle School will exceed capacity by the end of the six-year planning period. The approved CIP included an addition for this school, as well as future expenditures for a revitalization/expansion project. The addition project also will require reconfiguration of existing spaces and building systems upgrades to accommodate the larger numbers of students. Therefore, the Board of Education's requested FY 2019-2024 CIP included that the scope of the addition project be expanded to include these infrastructure and system upgrades while construction is on-site to make better use of fiscal resources. An FY 2019 appropriation was approved to begin planning this addition and facility upgrades project. An FY 2020 appropriation was approved for construction funds. The requested FY 2021-2026 CIP reflects an expanded scope for this project from an addition/facility upgrade to a replacement project, taking two years to construct. Therefore, the completion date is updated to September 2022 to reflect the full project scope. An FY 2021 appropriation was approved for the balance of construction funding. An FY 2022 appropriation was approved to complete this project. This project is scheduled to be completed August 2022.
project image
anchor

Phase

Preliminary Design Stage

Status

Pending Closeout
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP651910
Date Last Modified12/03/24
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY27FY28FY29FY30FY31FY32
Maintenance612102102102102102102
Energy228383838383838
NET IMPACT840140140140140140140
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY19
Appropriation FY28 Request0
Last FY's Cost Estimate62864
Cumulative Appropriation62864
Expenditure / Encumbrances0
Unencumbered Balance62864