Description

This project will design and implement a dedicated lane for Bus Rapid Transit in the median of U.S. 29 between Tech Road and Sligo Creek Parkway to improve travel time and service reliability. Alongside final design for a two-way busway, alternative technical concepts for one or zero dedicated transit lanes through Four Corners will be evaluated for construction-related impacts, transit performance, and cost. Adjacent neighborhood traffic impacts and potential mitigation will also be evaluated as part of final design. MCDOT will brief the T&E Committee after the analysis is completed and before proceeding to construction. The project will also assess the feasibility of master planned bicycle facilities along U.S. 29 within the project study limits.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Preliminary engineering began in FY23 and will be completed in FY26. Design is ongoing with Final Design to commence in FY28 and construction to begin in FY31. Construction of the BRT is expected to conclude in FY33, with operations beginning in FY34.
anchor

Cost Change

Cost change is due to addition of Final Design and Construction costs.
anchor

Justification

This project will complement the investment in U..S 29 Flash and improve transit travel time, reliability, performance, and person throughput from MD 198 to the Silver Spring Transit Center. These efforts will support master plan non-auto-driver mode share (NADMS) goals. Approved land use plans in the corridor recommend the implementation of transit lanes along with U.S. 29 Flash. The project is consistent with the Countywide Transit Corridors Functional Master Plan.
anchor

Fiscal Note

State aid reflects State grants for capital projects in Montgomery County programmed during the 2022 Maryland General Assembly Session.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland Department of Transportation, Washington Metropolitan Area Transit Authority, Maryland-National Capital Park and Planning Commission
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP502201
Date Last Modified05/26/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY22
Appropriation FY28 Request11730
Last FY's Cost Estimate9750
Cumulative Appropriation9750
Expenditure / Encumbrances5305
Unencumbered Balance4445