Description

Projections indicate that student enrollment at Burtonsville Elementary School will exceed capacity by the end of the six-year planning period. An FY 2023 appropriation was requested for planning funds to begin this project. Due to fiscal constraints, the County Council delayed the completion date for this project by two years, but maintained a portion of the planning funds. As part of the adopted FY2023-2028 CIP, an additional $3.0 million from the county executive's Prevailing Wage and Built to Learn Act PDFs was included in this project to maximize state aid. An FY 2024 appropriation and an amendment to the FY2023-2028 CIP was approved to construct a new Burtonsville ES at another location instead of building an addition at the existing school at the current location. An FY 2025 appropriation was approved for construction cost increases and for the balance of funding for this project. As a result of the relocation of Burtonsville ES, the completion date was accelerated one year, therefore, the scheduled completion date is August 2026.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

Final State Aid approved for $32,625,000 under the County's allocation of the Built To Learn Act school construction program which includes $2,718,000 for a net zero energy add-on. FY25 supplemental in State Aid for the amount of $1,285,000 from the Decarbonizing Public Schools Program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP652301
Date Last Modified04/15/26
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaFairland-Beltsville and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY23
Appropriation FY28 Request0
Last FY's Cost Estimate59061
Cumulative Appropriation59061
Expenditure / Encumbrances0
Unencumbered Balance59061