Description

This project provides for the acquisition, planning, design, construction, repair, renovation, reconstruction, site improvements, and capital equipping of an Olney community building. A community use space was originally planned to be delivered in conjunction with the renovation of the Olney Police Substation project. Due to site constraints, a meaningful community space is not feasible as part of the substation project. The Department of General Services, in collaboration with the Olney Chamber of Commerce, identified a separate site as a viable alternative.
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$5.2M Total
Expenditures/Funding
$5.2M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Site acquisition will occur in FY25. Renovation of the building is anticipated for FY26.
anchor

Justification

One of the goals of the 2005 Olney Master Plan is to create a civic center. The plan states that in 2000, the Olney Community Center Task Force, a joint effort by the Greater Olney Civic Association and the Olney Chamber of Commerce, requested that the County locate a permanent home for a number of County services. As the goal of creating a civic center has not been realized, this acquisition is an alternate way to provide community meeting space.
anchor

Other

Land cost will be transferred from Advance Land Acquisition Revolving Fund (ALARF): MCG (P316222).
anchor

Fiscal Note

State aid received in FY26 but building acquisition to occur in FY25 via Advance Land Acquisition Revolving Fund (ALARF).
anchor

Disclosures

The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Department of General Services, Mid-County Regional Services Center, Olney Chamber of Commerce, and State of Maryland.
Download & Explore
Budget Snapshot
$5.2M Total
Expenditures/Funding
$5.2M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP362506
Date Last Modified06/06/25
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryOther General Government
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision2000020010010000000
Land28000028002800000000
Site Improvements and Utilities00000000000
Construction00000000000
Other22000022000220000000
Total Expenditures52000052002900230000000
FUNDING (000s)
Funding SourceTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
State Aid52000052002900230000000
Total Funding Sources52000052002900230000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First Appropriation
Appropriation FY 26 Request5200
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0