up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the design and construction of a roadway extension of North High Street to Morningwood Drive in Olney. The project also provides a continuous 6-foot sidewalk on the south side of North High Street and ADA-compliant pedestrian access from Morningwood Drive. Additionally, about 500-feet of traffic calming curb bump-outs will be built along Morningwood Drive south of North High Street.
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design began in FY23 and will be completed in FY26. Land acquisition will begin in FY26 and construction will begin and be completed in FY27.
anchor

Cost Change

Project cost increase due to WSSC Water relocation design and rising construction costs.
anchor

Justification

The purpose of the project is to improve safety and enhance connectivity within the Olney town center vicinity. This project is supported by the Greater Olney Civic Association and will provide vehicular, pedestrian, and bicycle access to North High Street from Morningwood Drive instead of Georgia Avenue (MD 97). This project also supports the County Executive's Vision Zero initiative which aims to reduce injuries and fatalities on all roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Department of Permitting Services, Greater Olney Civic Association, Olney Town Center Advisory Committee
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor
Project NumberP502310
Date Last Modified01/09/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaOlney and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY27FY28FY29FY30FY31FY32
Maintenance25-55555
NET IMPACT25-55555
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request1348
Year First AppropriationFY23
Appropriation FY28 Request0
Last FY's Cost Estimate2419
Cumulative Appropriation2419
Expenditure / Encumbrances706
Unencumbered Balance1713
anchor
Download & Explore Project Details