up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for the replacement of the existing Dennis Avenue Bridge M-0194 over a tributary to Sligo Creek. The existing bridge, built in 1961, is a single span 30' structure composed of prestressed concrete voided slab beams carrying a 24' roadway, two 6' shoulders, and two 4'-8" sidewalks. The proposed replacement bridge will be a 80' overall span three-cell precast concrete arch culvert carrying a 22' roadway, two 5' bicycle compatible shoulders, two 2' striped buffers, a 13' shared-use path on the north side and a 7' sidewalk on the south side, for a total clear bridge width of 56'. The project includes utility relocations and approach roadway work at each end of the bridge as necessary to tie into the existing roadway and sidewalks. The bridge will be closed to traffic during construction. Accelerated bridge construction techniques will be utilized to minimize the disruption to the traveling public and local community.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Capacity

The roadway Average Daily Traffic (ADT) is approximately 14,000 vehicles per day.
anchor

Estimated Schedule

The design of the project and land acquisition was completed in FY25. The construction is scheduled to start in FY26 and be completed in FY27. The bridge will be closed to traffic during the summer of 2026.
anchor

Justification

The proposed replacement work will mitigate the frequent flooding of five residential properties and local streets upstream of the bridge; mitigate occasional roadway flooding on Dennis Avenue that causes significant traffic delays; and eliminate annual maintenance repairs required for this deteriorating structure. The existing bridge is rapidly deteriorating and is nearing the end of its estimated service life.
anchor

Other

The December 2018 Technical Update to the Master Plan of Highways and Transitways designates Dennis Avenue as Minor Arterial Road (MA-17) with a minimum right-of-way of 80'. The December 2018 Montgomery County Bicycle Master Plan recommends a sidepath (shared use path) on the north side. Streetlights, crosswalks, sidewalk ramps, bikeways, and other pertinent issues are being considered in the design of the project to ensure pedestrian safety.
anchor

Fiscal Note

The design costs for this project are covered in the Bridge Design Project (No. 509132). The project is eligible for 80 percent federal aid. The Intergovernmental funds are for WSSC Water relocations.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Federal Highway Administration - Federal Aid Bridge Replacement and Rehabilitation Program, Maryland State Highway Administration, Maryland Department of the Environment, Montgomery County Department of Environmental Protection, Montgomery County Department of Permitting Services, Montgomery County Public Schools, Montgomery County Department of Police, Montgomery County Fire and Rescue Service, Montgomery County Ride On, Maryland-National Capital Park and Planning Commission, Utilities, and Wheaton Regional Dam Flooding Mitigation (CIP Project #801710), and WSSC Water
Download & Explore Project Details
Budget Snapshot
0 M Total
Expenditures/Funding
0 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP501701
Date Last Modified01/08/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryBridges
Planning AreaKensington-Wheaton
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
FUNDING (000s)
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY27 Request0
Year First AppropriationFY22
Appropriation FY28 Request0
Last FY's Cost Estimate10870
Cumulative Appropriation10870
Expenditure / Encumbrances579
Unencumbered Balance10291
anchor
Download & Explore Project Details