up
Budget Year / Version:  
anchor
anchor
anchor

Description

In order to address the overutilization at the high school level in the Downcounty Consortium and at Walter Johnson High School, the Board of Education's approved FY 2019-2024 CIP includes three capital projects to address the overutilization in these areas. The approved CIP includes an expansion of Northwood High School, the reopening of Charles W. Woodward High School, and an addition at John F. Kennedy High School. The current Charles W. Woodward High School facility is significantly smaller than the proposed 2,700 student capacity. Therefore, the Board of Education's approved FY 2019-2024 CIP included funding to expand this facility when it reopens as a high school.

On March 25, 2019, the Board of Education approved that the Northwood High School addition/facility upgrades project be constructed with students off-site and that Northwood High School operate at the Charles W. Woodward High School as a temporary holding facility during the construction period. Therefore, based on the Board's approval, the Woodward facility will be used as a holding center for two years following initial construction of the new Charles W. Woodward High School facility. The addition/facility upgrades for Northwood High School is scheduled to be completed by September 2025. At that time, the Woodward High School facility will be reopened as a new high school. An FY 2021 appropriation was approved for construction funds. An FY 2022 appropriation is requested to continue this project.
project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$128.24M Total
Expenditures/Funding
$122.98M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Budget Snapshot
$128.24M Total
Expenditures/Funding
$122.98M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP651908
Date Last Modified11/17/20
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision8258402912312998213286600000
Land00000000000
Site Improvements and Utilities22091002209180606575595675075000
Construction93586009358631047199171773013642878224680
Other43000043000315011500000
Total Expenditures1282354029123112297541239305082483614392953224680
FUNDING (000s)
Funding SourceTotalThru FY20Rem FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds1282354029123112297541239305082483614392953224680
Total Funding Sources1282354029123112297541239305082483614392953224680
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request88690
Year First AppropriationFY19
Appropriation FY 22 Request4300
Last FY's Cost Estimate128235
Cumulative Appropriation123935
Expenditure / Encumbrances0
Unencumbered Balance123935