up
Budget Year / Version:  
anchor
anchor
anchor

Description

In order to address the overutilization at the high school level in the Downcounty Consortium and at Walter Johnson High School, the Board of Education's approved FY 2019-2024 CIP included three capital projects to address the overutilization in these areas. The approved CIP includes an expansion of Northwood High School, the reopening of Charles W. Woodward High School, and an addition at John F. Kennedy High School. The expansion of Northwood High School would increase the capacity to a 2,700 student capacity. The expansion of approximately 1,200 seats will require not only additional classrooms, but also reconfiguration of existing spaces and upgrades to building systems to accommodate the new student population. On March 25, 2019, the Board of Education approved that the Northwood High School project would be constructed with students off-site and that Northwood High School would operate at the Charles W. Woodward High School site as a temporary holding facility during the construction period. Therefore, based on the Board's approval, the Woodward facility would be used as a holding center for two years following initial construction of the new Charles W. Woodward High School facility, starting in August 2023. The addition/facility upgrades for Northwood High School were scheduled to be completed August 2025. At that time, the Woodward High School facility would be reopened as a new high school. An FY 2021 appropriation was approved for construction funds. An FY 2022 appropriation was approved to continue this project. An FY 2022 supplemental appropriation and transfer of funds of $4 million from the current revitalization/expansion project to this project was approved to address construction cost increases. An FY 2023 appropriation was requested for construction cost increases and construction funds to complete this project. While the increase in expenditures were approved, due to fiscal constraints, the County Council, as part of the adopted FY2023-2028 CIP, delayed this project one year. Therefore, Northwood High School will be relocated to the Charles W. Woodward High School site in August 2024, for two years. An FY 2024 appropriation and amendment to the FY 2023-2028 CIP was approved for additional funds due to the impact on construction costs as a result of the Covid-19 pandemic. This project is scheduled to be completed August 2026.
project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$196.1M Total
Expenditures/Funding
$136.85M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid reflects FY23 approved amount from the County's allocation of the Built To Learn Act school construction program and projected balance to be approved in the next fiscal year.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore
Budget Snapshot
$196.1M Total
Expenditures/Funding
$136.85M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP651908
Date Last Modified05/18/23
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision8258665360510001000000000
Land00000000000
Site Improvements and Utilities21649124811712745659567507500000
Construction161888151541949412724079371826738140318963100000
Other43000315011501150000000
Total Expenditures1960953428824961136846160431901738890318963100000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bond Premium55000550000000000
G.O. Bonds8173940298999687116812370122236160961986600
Recordation Tax2942029420000000000
Schools Impact Tax839839000000000
State Aid785970104626813592311531616654158001113400
Total Funding Sources1960953428824961136846160431901738890318963100000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request48860
Year First AppropriationFY19
Appropriation FY 24 Request15000
Last FY's Cost Estimate181095
Cumulative Appropriation181095
Expenditure / Encumbrances0
Unencumbered Balance181095