Description

The project provides for the planning of the of 3.5 mile Life Sciences Center Loop Trail, a 8 to12-foot wide shared use path that is a central feature of the Life Sciences Center (LSC) area of the Great Seneca Science Corridor Master Plan. The Life Sciences Center Loop Trail is a critical staging element to increasing the non-auto driver mode share (NADMS) prior to the expansion of stage 2 of the master plan's development. The shared use path will widen existing sidewalks along certain existing or planned streets in the Life Science Center (Omega Drive, Medical Center Drive, Johns Hopkins Drive, Belward Campus Drive, Decoverly Drive) as well as new roadways through the Public Safety Training Academy (PSTA) property and Crown Farm. The planning and design will create a trail design that is able to respond to varying right-of-way widths and other local conditions while providing a trail system that is recognizable and will attract walkers, runners and bicycle riders and will contribute to the LSC's sense of place. The design will enable both private developers and the county to build their respective pieces of the LSC loop in a consistent manner.
project image
anchor

Phase

Final Design Stage

Status

Active
anchor
Budget Snapshot
$12.9M Total
Expenditures/Funding
$11.47M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Preliminary design began in FY17 and was completed in FY18. Final design started in FY21 and should be completed in FY22. Land acquisition will start in FY25 and construction in FY26-27.
anchor

Justification

This project will enhance and improve pedestrian and bicycle mobility, help meet master plan non-auto-driver mode share (NADMS) goals and support the critical staging element to advance to stage 2 of the master plan's development.
anchor

Other

The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
anchor

Fiscal Note

Developer contributions of $11,471,000 are expected to fund land acquisition and construction.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Chambers of Commerce, City of Gaithersburg, City of Rockville, Department of General Services, Department of Permitting Services, Maryland-National Capital Park and Planning Commission, Maryland (MDOT) State Highway Administration, MDOT Maryland Transit Administration, Regional Service Centers, Universities at Shady Grove, Urban Districts, Utility Companies, Washington Metropolitan Area Transit Authority
Budget Snapshot
$12.9M Total
Expenditures/Funding
$11.47M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501742
Date Last Modified10/05/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaGaithersburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision232961781290000030060000
Land12000012000012000000
Site Improvements and Utilities00000000000
Construction93721093710003370600100
Other00000000000
Total Expenditures12901618812114710012003670660100
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Contributions1147100114710012003670660100
Current Revenue: General4003366400000000
G.O. Bonds103028274800000000
Total Funding Sources12901618812114710012003670660100
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28
Maintenance5-----5
Energy1-----1
NET IMPACT6-----6
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request0
Year First AppropriationFY17
Appropriation FY 24 Request0
Last FY's Cost Estimate12901
Cumulative Appropriation1430
Expenditure / Encumbrances1416
Unencumbered Balance14