Description

The County maintains approximately 1,099 lane-miles of primary and arterial roadways. This project provides for the systematic milling, pavement repair, and bituminous concrete resurfacing of selected primary and arterial roads and revitalization of others. This project provides for a systematic, full-service, and coordinated revitalization of the primary and arterial road infrastructure to ensure viability of the primary transportation network and enhance safety and ease of use for all users. Mileage of primary/arterial roads has been adjusted to conform with the inventory maintained by the State Highway Administration; this inventory is updated annually.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$114.79M Total
Expenditures/Funding
$43.8M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase is due to inflation and the addition of funding in FY29 and FY30.
anchor

Justification

Primary and arterial roadways provide transport support for tens of thousands of trips each day. Primary and arterial roads connect diverse origins and destinations that include commercial, retail, industrial, residential, places of worship, recreation, and community facilities. The repair of the County's primary and arterial roadway infrastructure is critical to mobility throughout the County. In addition, the state of disrepair of the primary and arterial roadway system causes travel delays, increased traffic congestion, and compromises the safety and ease of travel along all primary and arterial roads for drivers, pedestrians, and bicyclists. Well maintained road surfaces increase safety and assist in the relief of traffic congestion. In FY09, the Department of Transportation instituted a contemporary pavement management system. This system provides for systematic physical condition surveys and subsequent ratings of all primary/arterial pavements as well as calculating the rating health of the primary roadway network as a whole. Physical condition inspections of the pavements will occur on a two-to-three year cycle. The physical condition surveys note the type, level, and extent of primary/arterial pavement deterioration combined with average daily traffic and other usage characteristics. The 2022 pavement condition survey is used to calculate specific pavement ratings, types of repair strategies needed, and associated repair costs, as well as the overall Pavement Condition Index (PCI) of the entire primary/arterial network. The system also provides for budget optimization and recommends annual budgets for a systematic approach to maintaining a healthy primary/arterial pavement inventory.
anchor

Other

One aspect of this project will focus on improving pedestrian mobility by creating a safer walking and biking environment, utilizing selected engineering technologies, and ensuring Americans with Disabilities Act (ADA) compliance. The design and planning stages, as well as final completion of the project will comply with the Department of Transportation (DOT), Maryland State Highway Administration (MSHA), Manual on Uniform Traffic Control Devices (MUTCD), American Association of State Highway Officials (AASHTO), and ADA standards.
anchor

Fiscal Note

$17.6 million is the annual requirement to achieve a Countywide Pavement Condition Index of 80 for Primary/Arterial roads.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Expenditures will continue indefinitely.
anchor

Coordination

WSSC Water, Other Utilities, Montgomery County Department of Housing and Community Affairs, Montgomery County Public Schools, Maryland - National Capital Park and Planning Commission, Montgomery County Department of Permitting Services, Regional Services Centers, Community Associations, Montgomery County Pedestrian Safety Advisory Committee, Commission on People with Disabilities.
Download & Explore
Budget Snapshot
$114.79M Total
Expenditures/Funding
$43.8M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP508527
Date Last Modified01/08/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryHighway Maintenance
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision583902024381510127935673359610120
Land00000000000
Site Improvements and Utilities364036400000000
Construction108551637244842399856288650767336965720462880
Other3636000000000
Total Expenditures114790637607230438007300730073007300730073000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bond Premium50005000000000000
G.O. Bonds99859488297230438007300730073007300730073000
PAYGO61256125000000000
Recordation Tax Premium (MCG)38063806000000000
Total Funding Sources114790637607230438007300730073007300730073000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request7300
Year First AppropriationFY85
Appropriation FY 26 Request7300
Last FY's Cost Estimate97990
Cumulative Appropriation70990
Expenditure / Encumbrances64171
Unencumbered Balance6819