up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for design, right-of-way acquisition, utility relocations, and construction of a new grade separated connection under Georgia Avenue to improve access to the Forest Glen Metro Station from neighborhoods and institutions located on the east side of Georgia Avenue. There is currently an underground walkway from the parking and bus area on the northwest quadrant of the intersection to the southwest quadrant. A new connection would be made to this passageway connecting the southwest quadrant to the northeast quadrant. A ramp connection and elevators bring the underground connection to grade on the northeast corner of the intersection. Associated sidewalk improvements would also be made to Forest Glen Road to complete the walking connection on the north side of the road to Holy Cross Hospital.

project image
anchor

Phase

Preliminary Design Stage

Status

New
anchor
Budget Snapshot
$20.15M Total
Expenditures/Funding
$15.2M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

This project is needed to improve the mobility, and safety for all facility users within the project area by reducing existing conflicts between pedestrians and vehicles. Currently, transit users, pedestrians, and bicyclists cross MD 97 (Georgia Avenue) and Forest Glen Road to access the Metro Station. This project will eliminate the need for these at-grade pedestrian crossings and will also facilitate crossing of the road for community members who are not using Metro. Traffic volumes and speeds on MD 97 can be very high and pedestrians must cross over eight lanes of traffic. These crossings can be very intimidating, reducing community connectivity and use of the Forest Glen Metro Station.

anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress.
anchor

Coordination

Maryland-National Capital Park & Planning Commission, Maryland State Highway Administration, Washington Metropolitan Area Transit Authority.

Download & Explore
Budget Snapshot
$20.15M Total
Expenditures/Funding
$15.2M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP501911
Date Last Modified05/29/18
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaKemp Mill-Four Corners and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
Planning, Design and Supervision43500039000015001500450450450
Land10000010000001000000
Site Improvements and Utilities130000130000006506500
Construction135000090000000450045004500
Other00000000000
Total Expenditures2015000152000015002500560056004950
FUNDING (000s)
Funding SourceTotalThru FY17Est FY18Total 6 YearsFY 19FY 20FY 21FY 22FY 23FY 24Beyond 6 Years
G.O. Bonds2015000152000015002500560056004950
Total Funding Sources2015000152000015002500560056004950
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 19 Request0
Year First Appropriation
Appropriation FY 20 Request0
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0