Description

This project provides for design, engineering plans, and construction for three new roads and master planned bikeways in the White Flint District East side area, as follows: 1. Executive Boulevard Extended (East) (B-7) - Rockville Pike/MD 355 to a New Private Street - construct 1,100 feet of four-lane roadway; 2. Executive Boulevard Extended (East) (B-7) - New Private Street to new Nebel Street Extended - construct 600 feet of four-lane roadway; 3. Nebel Street (B-5) - Nicholson Lane South to a Combined Property site - construct 1,200 feet of four-lane roadway. Bikeway design and construction will be consistent with the adopted master plan staging requirements. Various improvements to the roads will include new traffic lanes, shared-use paths, the undergrounding of overhead utility lines where required, other utility relocations, and streetscaping. These projects will become standalone projects once engineering is complete and final construction costs can be accurately determined. This project also assumes the developers will dedicate the land needed for these sub-projects in a timely manner. However, no agreements have been made for the land dedication so far. Also, this project previously included a new bridge across the WMATA tracks as an extension of future McGrath Boulevard. This bridge is no longer part of the plan for the redevelopment of the WMATA site, and has been removed from this scope and cost estimate.

project image
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$45.66M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Remaining design work and all construction has been delayed beyond FY32 due to affordability and other factors. Concept design of all road projects began FY12 and has been delayed due to coordination with stakeholders. Construction of Executive Boulevard Extended East from Rockville Pike/MD 355 to a New Private Street was delayed due to tax district affordability. Design of Executive Boulevard East Extended was delayed due to coordination between stakeholders over the alignment.

anchor

Cost Change

Construction cost increases are based on unit costs from similar past projects, not detailed designs. Final costs will be determined after the 35% preliminary engineering phase. Current estimates are substantially higher than those from FY12 due to inflation and rising material and labor costs.

anchor

Justification

The vision for the White Flint District is for a more urban core with a walkable street grid, sidewalks, bikeways, trails, paths, public use space, parks and recreational facilities, mixed-use development, and enhanced streetscape to improve the areas for pedestrian circulation and transit-oriented development around the Metro station. These road improvements, along with other District roads proposed to be constructed by developers will fulfill the strategic program plan for a more effective and efficient transportation system. The proposed improvements are in conformance with the White Flint Sector Plan Resolution 16-1300 adopted March 23, 2010.
anchor

Fiscal Note

Funding Sources: The ultimate funding source for these projects will be White Flint Development District Tax revenues and related special obligation bond issues. Debt service on the special obligation bonds will be paid solely from White Flint Special Taxing District revenues. Updated Cost Estimation (FY 26): Construction cost estimates are based on concepts projected from unit length costs of similar prior projects and are not based on quantity estimates or engineering designs. Final construction costs will be determined after the preliminary engineering (35%) phase.

anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, White Flint Sector Plan, Washington Metropolitan Area Transit Authority, Maryland State Highway Administration, Federal Agencies including the Nuclear Regulatory Commission, Developers, Department of Environmental Protection, Department of Permitting Services
Budget Snapshot
$45.66M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP501204
Date Last Modified10/02/25
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaNorth Bethesda-Garrett Park
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision93407551900000008566
Land22000000000
Site Improvements and Utilities76150000000007615
Construction2870500000000028705
Other00000000000
Total Expenditures4566275719000000044886
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
White Flint Special Tax District4566275719000000044886
Total Funding Sources4566275719000000044886
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY14
Appropriation FY 28 Request0
Last FY's Cost Estimate29690
Cumulative Appropriation776
Expenditure / Encumbrances757
Unencumbered Balance19