Description

This project provides funds for the study and prioritization of improvements to Dedicated but Unmaintained (DBU) County Roads in order to accept them into the County's road maintenance system. Once the need and priority of the roadway improvements are established, funding will be provided for their design and construction. As stipulated in the DBU County Roads Policy, the County will fund planning, design and supervision costs up to 10 percent of the total cost of each project. The remaining costs for these projects will be recovered from the communities through a special tax assessment. The DBU County Roads Policy was developed by the DBU County Roads Working Group. The policy provides guidance for County officials in responding to requests from residents for improvements to, or maintenance of, DBU County Roads in a consistent manner and establishes criteria for evaluating the need for improvements to the DBU County Roads.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$0.76M Total
Expenditures/Funding
$0.03M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost decrease due to savings in prior years. FY29-30 added to this level of effort project.
anchor

Justification

A total of 59 roads have currently been identified and inventoried as DBU County Roads. In the past, residents have requested that the County assume maintenance of various non-standard roads even though County policy prohibits acceptance of maintenance responsibilities for roadways that do not meet appropriate County standards. The purpose of this project is to respond to these requests in accordance with the recently adopted DBU County Roads Policy. Under the terms of the policy, citizen requests will result in comparative studies of the DBU County Roads being performed to determine the priority and ranking of the requested projects.
anchor

Other

DOT completed a re-evaluation report in FY22 and recommended maintaining this program.
anchor

Fiscal Note

Annual level of effort funding is provided to develop initial responses to community requests. Funding to complete studies beyond the current appropriation limit or for design and construction will be added as road improvement projects are identified and recommended through this program.
anchor

Coordination

Montgomery County Department of Permitting Services, Montgomery County Department of Finance, Montgomery County Civic Federation
Budget Snapshot
$0.76M Total
Expenditures/Funding
$0.03M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP501117
Date Last Modified12/21/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision41137110305555550
Land1414000000000
Site Improvements and Utilities00000000000
Construction337337000000000
Other00000000000
Total Expenditures76272210305555550
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Current Revenue: General40010305555550
G.O. Bonds722722000000000
Total Funding Sources76272210305555550
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request-12
Year First AppropriationFY11
Appropriation FY 26 Request5
Last FY's Cost Estimate769
Cumulative Appropriation749
Expenditure / Encumbrances722
Unencumbered Balance27