This project provides repairs and renovations to parking lots at transit park and ride lots and transit centers to allow them to continue functioning as transit facilities and comply with Americans with Disabilities Act (ADA) requirements. In FY08/FY09, an evaluation and assessment of all park and ride facilities, including ADA accessibility and pedestrian safety, was completed to provide scope and detailed cost estimates for the restoration and upgrades. An updated comprehensive study will evaluate the condition of the County's park and ride lots and establish priorities for site improvements and development with the goal of increasing usage of the facilities and enhancing amenities.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$7.14M Total
Expenditures/Funding
$1.1M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Conduct evaluation of existing lots in FY31 and implement improvements, repairs and renovations beginning in FY32.
anchor

Cost Change

Cost change is due to addition of a comprehensive study and implementation of the study's recommendations for site improvements.
anchor

Justification

The County operates eight transit park and ride lots and three transit centers in major transportation corridors. Several County park and ride lots have had major failures, resulting from the age and use of the facilities. Some of the lots were constructed more than 20 years ago. Pavement and the entrances were not constructed to support heavy bus traffic.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Department of Permitting Services, Maryland-National Capital Park and Planning Commission, Utilities, Department of Environmental Protection
Download & Explore Project Details
Budget Snapshot
$7.14M Total
Expenditures/Funding
$1.1M 6 Year Total
Expenditures/Funding
anchor
Project NumberP500534
Date Last Modified01/06/26
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision122237204500000350100400
Land00000000000
Site Improvements and Utilities55000000000
Construction2416174719650000006500
Other3496896000000002600
Total Expenditures7139302019110000003507503000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
G.O. Bonds7139302019110000003507503000
Total Funding Sources7139302019110000003507503000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY05
Appropriation FY 28 Request0
Last FY's Cost Estimate3039
Cumulative Appropriation3039
Expenditure / Encumbrances3038
Unencumbered Balance1