anchor

Description

This project provides repairs and renovations to parking lots at transit park and ride lots and transit centers to allow them to continue functioning as transit facilities and comply with Americans with Disabilities Act (ADA) requirements. In FY08/FY09, an evaluation and assessment of all park and ride facilities, including ADA accessibility and pedestrian safety, was completed to provide scope and detailed cost estimates for the restoration and upgrades.
anchor

Phase

Under Construction

Status

Pending Closeout
anchor
Budget Snapshot
$3.04M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Justification

The County operates 8 transit park and ride lots and 3 transit centers in major transportation corridors. Several County park and ride lots have had major failures, resulting from the age and use of the facilities. Some of the lots were constructed more than 20 years ago. Pavement and the entrances were not constructed to support heavy bus traffic.
anchor

Fiscal Note

Funding for this project is general obligation bonds dedicated to Mass Transit with debt service financed from the Mass Transit Facilities Fund.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland State Highway Administration, Department of Permitting Services, Maryland-National Capital Park and Planning Commission, Utilities, Department of Environmental Protection
Download & Explore
Budget Snapshot
$3.04M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP500534
Date Last Modified12/21/23
Administering AgencyTransportation
CategoryTransportation
SubCategoryMass Transit (MCG)
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision342342000000000
Land00000000000
Site Improvements and Utilities55000000000
Construction179617306600000000
Other896896000000000
Total Expenditures303929736600000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds303929736600000000
Total Funding Sources303929736600000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY05
Appropriation FY 26 Request0
Last FY's Cost Estimate3039
Cumulative Appropriation3039
Expenditure / Encumbrances2997
Unencumbered Balance42