Description

This project provides funding for modifications to College facilities to comply with the accessibility provisions of the Americans with Disability Act (ADA) of 1990. Typical modifications include: paths of travel, entrance doors, stairs, corridors, ramps, toilet facilities, drinking fountains, parking, curb cuts, elevators, areas of refuge, public phones, signage, emergency notification and alarm systems, and other accessibility modifications to meet comfort, security, and safety requirements for people with disabilities. This project addresses access deficiencies in all College facilities. Project implementation is in accordance with ADA guidelines and the College's annual work program. The College has conducted a series of facility audits to determine ADA compliance and scope of required modification work, including estimated costs. Readily achievable modifications are implemented as part of the College's regular maintenance work.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$2.25M Total
Expenditures/Funding
$0.45M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to addition of FY29 and FY30.
anchor

Justification

The ADA requirements mandate a comprehensive effort to provide accessible programs and barrier free facilities to disabled persons. The deadline for compliance with the requirement to make the College's programs accessible was January 26, 1995; however, the law allows for additional time to comply if available resources are limited for structural and building modifications. Based on the College's annual work program and available funding for ADA modifications, the College anticipates that the project will continue beyond the current six-year CIP. Relevant studies include the Montgomery College 2025 Strategic Plan, Collegewide Facilities Condition Assessment Update (1/23) and the Collegewide Facilities Master Plan Update (Pending 2023).
anchor

Other

FY25 Appropriation: $75,000 (G.O. Bonds). FY26 Appropriation: $75,000 (G.O. Bonds). The following fund transfer has been made from this project: $7,000 to Planning, Design & Construction project (No. P906605) (BOT Resol. #01-153 - 10/15/01).
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

This project is coordinated with the scheduled building renovations, and the planned construction of new buildings, on the Rockville, Germantown and Takoma Park/Silver Spring Campuses.
Download & Explore
Budget Snapshot
$2.25M Total
Expenditures/Funding
$0.45M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP936660
Date Last Modified09/18/23
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision18814525183333330
Land00000000000
Site Improvements and Utilities235234100000000
Construction18309344644327272727272720
Other00000000000
Total Expenditures225313134904507575757575750
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds225313134904507575757575750
Total Funding Sources225313134904507575757575750
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request75
Year First AppropriationFY93
Appropriation FY 26 Request75
Last FY's Cost Estimate2103
Cumulative Appropriation1803
Expenditure / Encumbrances1313
Unencumbered Balance490