This project provides funding for the renovation of the libraries on two of Montgomery College's campuses, specifically the Rockville Macklin Tower Building, and the Takoma Park/Silver Spring Resource Center. An architecture firm has developed conceptual designs for the two campus libraries, and has identified improvements required to support organizational and service changes, and to modernize the libraries. The main library floors will be hubs of academic life at Montgomery College: dynamic spaces that will be student-centered, technology and service-driven, and will foster innovation. The upper floors will provide students with comfortable and quiet study spaces and smaller, curated collections to support their academic and career goals. Additional goals of this project is to meet the variety of student needs including group study, individual study, and silent study.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$42.04M Total
Expenditures/Funding
$25.52M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

A part1/part 2 document was completed in FY21 for the Takoma Park/Silver Spring library renovation. Design will start in FY22, construction will begin in FY23, and continue in FY24, with completion in FY24. The Rockville library project design will begin in FY24, and construction, and FFE will be requested in FY25 and FY26.
anchor

Cost Change

State aid escalation of 5 percent approved for FY25 as well as a $650,00 transfer to cover cost increases prior to FY25.
anchor

Justification

The Takoma Park/Silver Spring Resource Center was constructed in 1978, and is 45 years old. The Rockville Macklin Tower Building was constructed in 1971 and is 52 years old. These two buildings are outdated, space and service configuration is insufficient, employee workspaces are inadequate to promote collaboration with colleagues, as well as, support student success. In FY16, the Montgomery College Libraries had nearly 670,000 visitors, and ethnographic studies have shown that libraries are one of the places at Montgomery College where students can escape from work and family obligations to get homework and studying done. In addition, Montgomery College's libraries provide students access to technology to be successful in their coursework. In FY16, the Montgomery College library's computers, laptops, and tablets were used approximately 200,000 times by nearly 18,000 unique users. Providing computers, laptops, tablets, software, scanners, internet, and accessible software programs improves college affordability for students who wouldn't otherwise be able to afford those tools. The Montgomery College Libraries increasingly support educational excellence by embedding librarians and information literacy into classes with 7,600 students taught. Other relevant studies and plans include the Libraries Master Plan (2015), Montgomery College Libraries' Ethnographic Studies 2013-2016 (2016), Collegewide Facilities Master Plan (Pending 2023), Libraries Planning Study (6/17), and Libraries Planning Study Germantown Addendum (9/17), and Montgomery College Strategic Plan (7/23).
anchor

Other

FY25 Appropriation: Total $2,000,000 ($1,000,000 (GO Bonds); and $1,000,000 (State Aid)). FY26 Appropriation: Total $21,570,000 ($10,785,000 (GO Bonds); and $10,785,000 (State Aid)).

A fund transfer was made to this project: $650,000 from the Planning, Design and Construction project (#P906605)(BOT Resol. #23-06-093, 06/21/23).

anchor

Fiscal Note

$650,000 transferred from Planning, Design, and Construction project (906605) to Collegewide Library Renovations project (661901) in the FY21-26 CIP (BOT Resolution:21-06-069 adopted on 6/21/2021).
anchor

Disclosures

Montgomery College asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Download & Explore
Budget Snapshot
$42.04M Total
Expenditures/Funding
$25.52M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP661901
Date Last Modified05/20/24
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision54361126235619541954000000
Land00000000000
Site Improvements and Utilities00000000000
Construction33202799042122100020001900000000
Other3398082825700257000000
Total Expenditures42036911673962552439542157000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds21343455840231276219771078500000
State Aid20693455833731276219771078500000
Total Funding Sources42036911673962552439542157000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request2000
Year First AppropriationFY20
Appropriation FY 26 Request21570
Last FY's Cost Estimate40262
Cumulative Appropriation18466
Expenditure / Encumbrances9446