Description

This project provides funding for the capital renewal and major renovation of College facilities for new and changing College academic programs and student service operations. The major focus of this project is to support programmatic changes to College facilities and operations by allowing the College to continue an on-going building modernization effort where State aid is lacking. With this project, the College will selectively focus State aid requests on high cost projects utilizing these County funds to support an on-going renovation effort on each campus. In conjunction with programmatic improvements and modifications, this project will replace aging building systems, such as heating, air conditioning, electrical, plumbing, etc., provide furniture, fixtures, and equipment; and update facilities to current building codes and regulations.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$36.85M Total
Expenditures/Funding
$12M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to addition of FY29 and FY30.
anchor

Justification

Starting FY2009, the County approved funding several renovation projects from the Capital Renewal project. These renovation projects were less likely to receive funding from the State, and as a result five projects at that time were merged into the Capital Renewal project. In November 2007, the College updated a comprehensive building system/equipment assessment, including site utilities and improvements, that identified deficiencies, prioritized replacements and upgrades, and provides the framework for implementing a systematic capital renewal program to complement on-going preventive maintenance efforts. The College continues to have a significant backlog of major building systems and equipment renovations and/or replacements due to the age of the Campuses and deferral of major equipment replacement. Key components of the HVAC, mechanical and electrical systems are outdated, energy inefficient, and costly to continue to repair. The renovation and/or replacement of major building systems, building components and equipment, and site improvements will significantly extend the useful life of the College's buildings and correct safety and environmental problems. The Collegewide Facilities Condition Assessment identified a $104 million deferred maintenance backlog over the next five years, for the three campuses. The total deferred maintenance backlog totals $345 million. If additional financial resources are not directed at this problem, College facilities will continue to deteriorate leading to higher cost renovations or building replacements. Related studies include the Montgomery College Strategic Plan (7/23). Collegewide Facilities Condition Assessment (1/23), and Collegewide Facilities Master Plan (Pending 2023), and Collegewide Utilities Master Plan (6/22).
anchor

Other

FY25 Appropriation: $2,000,000 (G.O. Bonds). FY26 Appropriation: $2,000,000 (G.O. Bonds).
A fund transfer was made from this project: $2,100,000 to the TPSS Math and Science Center project (#P0076607) (BOT Resol. #23-06-093, and #23-06-094, 06/21/23).
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Energy Conservation: College (CIP No. P816611), Facility Planning: College (CIP No. P886686), Planned Lifecycle Asset Replacement: College (CIP No. P926659), Roof Replacement: College (CIP No. P876664), Site Improvements: College (CIP No. P076601)
Download & Explore
Budget Snapshot
$36.85M Total
Expenditures/Funding
$12M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP096600
Date Last Modified01/05/24
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision48221533148918003003003003003003000
Land00000000000
Site Improvements and Utilities00000000000
Construction29351153553796102001700170017001700170017000
Other2673226540800000000
Total Expenditures36846191535693120002000200020002000200020000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds36846191535693120002000200020002000200020000
Total Funding Sources36846191535693120002000200020002000200020000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request2000
Year First AppropriationFY09
Appropriation FY 26 Request2000
Last FY's Cost Estimate34946
Cumulative Appropriation24846
Expenditure / Encumbrances19215
Unencumbered Balance5631