Description

This project funds the replacement of the current runway lighting system at the Airpark property with LED lighting, which will provide increased visibility and will comply with Federal Aviation Administration (FAA) standards.
anchor

Phase

Planning Stage

Status

Pending Closeout
anchor
Budget Snapshot
$1.18M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Cost Change

Cost change reflects actual costs associated instead of estimates.

anchor

Justification

This project is a continuation of the Airport Layout Plan (ALP), which was developed in conjunction with the FAA in 2002. The ALP identifies the projects and plans the sequencing for continued airport improvement. A supplemental environmental assessment for this purchase was completed in 2017. This project includes the purchase of land adjacent to the Airpark which is necessary to maintain Federal safety standards for airport operations. Federal funds for the Airpark are approved by the FAA through the Airport Capital Improvement Plan (ACIP). FAA priorities for funding airport projects include promoting safety and security; preserving existing infrastructure; mitigating noise or environmental impacts; fulfilling compliance, and providing capacity. Federal funding and requirements will dictate the final timeline for the purchase.
anchor

Coordination

Federal Aviation Administration and Maryland Aviation Administration.
Download & Explore Project Details
Budget Snapshot
$1.18M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project NumberP392308
Date Last Modified01/07/26
Administering AgencyRevenue Authority
CategoryRevenue Authority
SubCategoryMiscellaneous Projects (Revenue Authority)
Planning AreaGaithersburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision233023300000000
Land00000000000
Site Improvements and Utilities950095000000000
Construction00000000000
Other00000000000
Total Expenditures11830118300000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Federal Aid11240112400000000
Revenue Authority3503500000000
State Aid2402400000000
Total Funding Sources11830118300000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First Appropriation
Appropriation FY 28 Request0
Last FY's Cost Estimate1320
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0