Description

This project funds modifications of existing park buildings and facilities to modernize equipment, produce energy, control and utility costs. Work includes, but is not limited to, identifying, planning, implementing, and monitoring effective energy conservation measures at various park facilities. Emphasis is placed upon positive and proven measures to remedy heat losses and gains through modifications to building envelope systems and through improvement and retrofit of building support systems. Improvements may also include modification of electrical/mechanical/HVAC systems and equipment and their associated control and distribution systems, as well as lighting upgrades, utility supply upgrades, PV systems, other energy conservation improvements, and solar initiatives.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$1.85M Total
Expenditures/Funding
$0.75M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Increase due to the addition of FY31 and FY32 to this ongoing project.
anchor

Justification

This project supports the modernization of existing park buildings and facilities to improve energy efficiency, reduce utility costs, and upgrade outdated equipment. Efforts include identifying and implementing energy conservation measures across various park sites, as well as ongoing planning and monitoring to ensure long-term sustainability and operational effectiveness.
anchor

Fiscal Note

Prior year partial capitalization of expenditures through FY16 totaled $531,000.
anchor

Disclosures

Expenditures will continue indefinitely.
Download & Explore Project Details
Budget Snapshot
$1.85M Total
Expenditures/Funding
$0.75M 6 Year Total
Expenditures/Funding
anchor
Project NumberP998710
Date Last Modified11/12/25
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision5051411761884242262626260
Land00000000000
Site Improvements and Utilities00000000000
Construction13423913895628383999999990
Other00000000000
Total Expenditures18475325657501251251251251251250
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
M-NCPPC Bonds18475325657501251251251251251250
Total Funding Sources18475325657501251251251251251250
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request125
Year First AppropriationFY99
Appropriation FY 28 Request125
Last FY's Cost Estimate1597
Cumulative Appropriation1097
Expenditure / Encumbrances533
Unencumbered Balance564