Budget Year / Version:  
anchor
anchor
anchor

Description

This project schedules renovation, protection, modernization, conversion, restoration, and/or replacement of aging, unsafe, or obsolete local park facilities and features. The park system contains hundreds of local parks and many different types of facilities, many of which are over 40 years old. Improvements may include, but are not limited to, renovating and/or converting existing amenities, restorations, modernizing facilities, improving infrastructure, etc.

anchor

Phase

Ongoing

Status

New
anchor
Budget Snapshot
$23.86M Total
Expenditures/Funding
$23.86M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Level of effort increase reflect construction cost to rehabilitate aging infrastructure. Also cost increase is due to addition of two fiscal years to this ongoing project and the combination of all PLAR local subprojects into the main PLAR Local Parks PDF (P967754). Added increase in FY25 due to addition of State Aid funding.
anchor

Justification

Renovations scheduled in this project are based on ongoing infrastructure assessments, as well as requests from park operations. Failure to proactively renovate or replace aging park facilities and features before the end of their useful life results in decreased levels of service to park users, potential safety risks, and an overall increase in capital costs as repairs become emergencies.
anchor

Fiscal Note

M-NCPPC was awarded $1,195,000 of FY24 State Bond Bills for the following: Minor Renovations - Maplewood Alta Vista Park ($500k), Wheaton Forest Local Park ($195k); Play Equipment - Greenwood Local Park ($250k), McKnew Local Park ($250k). The fiscal note has been updated to reflect the addition of $150,000 in State Aid funding for Merrimac Playground, attributed to a $1,150,000 increase in State Bond Bills.


anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. Expenditures will continue indefinitely. M-NCPPC asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Trails: Hard Surface Renovation, PDF 888754, Trails: Natural Surface Trails, PDF 858710
Download & Explore
Budget Snapshot
$23.86M Total
Expenditures/Funding
$23.86M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP872503
Date Last Modified05/20/24
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision26240026244494524234264374370
Land00000000000
Site Improvements and Utilities2123600212363636365635783600346932970
Construction00000000000
Other00000000000
Total Expenditures2386000238604085410840014026390637340
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
M-NCPPC Bonds2371000237103935410840014026390637340
State Aid15000150150000000
Total Funding Sources2386000238604085410840014026390637340
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request4085
Year First Appropriation
Appropriation FY 26 Request4108
Last FY's Cost Estimate0
Cumulative Appropriation0
Expenditure / Encumbrances0
Unencumbered Balance0