Description

This project has supported a myriad of enhancements related to the County's life sciences and entrepreneurial climate. This project originally provided funds to design and construct the public amenities at the Shady Grove Life Sciences Center. The project has supported the development and land use plans for the Germantown Life Sciences Park (GLSP) and the Site II development. Additionally, the project has supported the development of the Germantown and Rockville business incubators and upgrades to the Silver Spring Incubator. Specific tasks included feasibility studies, due diligence, refining Programs of Requirements (PORs), design and construction. Additions to the original project scope included: revised development and subdivision plans to increase site density (FY00); subdivision plans for prospective Life Sciences and Technology Centers (FY03); planning for the Rockville Incubator (FY07); and the pursuit of all needed steps for Site II to be accepted into the Maryland Voluntary Clean-Up Program (FY11). This project may also be used for incubator renovations, the preliminary development of other incubators, tech parks, or other economic development capital projects should future new opportunities become available. In FY22, funds were provided for the conversion of excess office space into wet labs in the lab corridor of the Germantown Incubator. In FY25, the project added funds to support the continued conversion of vacant offices at the Germantown center into wet labs, including the partitioning of labs into bench space. This funding also supports the refresh of the co-working space at the Rockville center, and the branding and technology improvements of the centers. In FY25, a portion of appropriated funds are to be expended for tenant improvements at the initial location of the Montgomery County-branded AI Innovation Center.
project image
anchor

Phase

Ongoing

Status

Pending Closeout
anchor
Budget Snapshot
$6.67M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Tenant improvements at the Montgomery County-branded AI Innovation Center are expected to begin in the latter half of FY26 and FY27.
anchor

Justification

For the past five years the Germantown Incubator has had excess office space and insufficient wet lab space to meet the demand of small life science companies. The labs are routinely at 100 percent occupancy while the office space is routinely 28-44 percent vacant. Generally each lab company also occupies office space. By increasing the number of available wet labs, the incubator can serve more emerging life science companies by providing both lab and office space, thereby reducing the current office space vacancy. Improving the County's facilities will maximize potential use of space, including innovation, collaboration spaces, shared labs with bench rentals and shared equipment, etc. to transition the facilities to experienced globally recognized innovation ecosystem activators incorporating expanded programming and technical assistance.
anchor

Other

The original component of the Capital Improvements Program project, the construction of all required amenities and improvements to meet M-NCPPC's subdivision requirement for the SGLSC property, is complete. The Rockville Innovation Center and the Germantown Innovation Center have been open for business. Site II was accepted into the Maryland Voluntary Clean-Up Program and has been conveyed to Percontee. The Silver Spring Innovation Center has been renovated.
anchor

Coordination

State of Maryland, TEDCO, Maryland Department of Public Works and Transportation - Division of Capital Development, the Maryland-National Capital Park and Planning Commission, Montgomery County Economic Development Corporation, and tenants of the Germantown Innovation Center. Facility Planning: Montgomery County Government, Montgomery College, WSSC Water, and private developers
Download & Explore Project Details
Budget Snapshot
$6.67M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project NumberP789057
Date Last Modified01/06/26
Administering AgencyCounty Executive
CategoryGeneral Government
SubCategoryEconomic Development
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision3369323313600000000
Land3939000000000
Site Improvements and Utilities7373000000000
Construction3177175300200000000
Other1212000000000
Total Expenditures66703532313800000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Current Revenue: General54002262313800000000
G.O. Bonds410410000000000
PAYGO260260000000000
Recordation Tax Premium (MCG)600600000000000
State Aid00000000000
Total Funding Sources66703532313800000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY90
Appropriation FY 28 Request0
Last FY's Cost Estimate6670
Cumulative Appropriation6670
Expenditure / Encumbrances3670
Unencumbered Balance3000