up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides funding for identifying and preparing a site for the installation of a memorial in remembrance of the known victims of lynching in Montgomery County.
anchor

Phase

Under Construction

Status

Closeout
anchor
Budget Snapshot
$0.05M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

Established in 2018, the Montgomery County Remembrance and Reconciliation Commission's goal is to build a community dialogue about our racial history, and how to promote reconciliation, peace, and justice. Part of the Commission's work plan is to partner with the Alabama-based Equal Justice Initiative (EJI) and other stakeholders to help our County claim and install a monument commemorating the three Montgomery County locations where lynchings have been documented. While EJI manufactures and ships the County's memorial, additional expenses, including planning and installation of the memorial, identifying the land, and constructing the site around it, are local responsibilities that will be funded through this project.
anchor

Coordination

The Office of Human Rights, Office of Racial Equity and Social Justice, Department of General Services, and Equal Justice Initiative.
Download & Explore Project Details
Budget Snapshot
$0.05M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project NumberP362308
Date Last Modified11/25/25
Administering AgencyGeneral Services
CategoryGeneral Government
SubCategoryOther General Government
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Planning, Design and Supervision00000000000
Land00000000000
Site Improvements and Utilities1717000000000
Construction00000000000
Other3333000000000
Total Expenditures5050000000000
FUNDING (000s)
Funding SourceTotalThru FY25Est FY26Total 6 YearsFY 27FY 28FY 29FY 30FY 31FY 32Beyond 6 Years
Current Revenue: General5050000000000
Total Funding Sources5050000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 27 Request0
Year First AppropriationFY23
Appropriation FY 28 Request0
Last FY's Cost Estimate50
Cumulative Appropriation50
Expenditure / Encumbrances50
Unencumbered Balance0
anchor
Download & Explore Project Details