Description

This level of effort project is intended to provide a structured process to ensure safe pool operations through the repair or replacement of slides. A facilities assessment has been conducted to evaluate the needed level of repair or replacement and to create a priority list.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$13.42M Total
Expenditures/Funding
$10.75M 6 Year Total
Expenditures/Funding
anchor

Estimated Schedule

Slide repairs will be coordinated with the annual closure of indoor and outdoor pools to minimize the impact of construction on pool operations. The tentative replacement schedule is: FY25: Eunice Kennedy/Sargent Shriver Indoor Pool, FY26: Germantown Outdoor Pool, FY27: Wheaton Glenmont Outdoor Pool, FY28: Bethesda Outdoor Pool, FY29: Long Branch Outdoor Pool, FY30: Germantown Indoor Pool.
anchor

Justification

Most slides were constructed many years ago and many have disintegrated slide surfaces or rusted structural elements which could create safety issues if not repaired. This project ensures that slides are repaired in a systematic sequence based on their condition. The exact cost of slide repair or replacement will be determined based on more detailed studies that will be performed during the design and engineering phase of each slide.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Department of Recreation and Department of General Services.
Budget Snapshot
$13.42M Total
Expenditures/Funding
$10.75M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP722101
Date Last Modified03/02/25
Administering AgencyGeneral Services
CategoryCulture and Recreation
SubCategoryRecreation
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision329035056323774633993814083633630
Land00000000000
Site Improvements and Utilities00000000000
Construction10130105270183771920139212801447116911690
Other00000000000
Total Expenditures1342014021264107542383179116611855153215320
FUNDING (000s)
Funding SourceTotalThru FY24Rem FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds121191011264107542383179116611855153215320
PAYGO13011301000000000
Total Funding Sources1342014021264107542383179116611855153215320
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request1960
Year First AppropriationFY22
Appropriation FY 26 Request1791
Last FY's Cost Estimate13420
Cumulative Appropriation5049
Expenditure / Encumbrances2051