Description

This project involves the site selection for a future one million gallon elevated storage facility in the HG760 water pressure zone.
anchor

Phase

TBA

Status

Pending Closeout
anchor
Budget Snapshot
$7.21M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

Budget Snapshot
$7.21M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP973819
Date Last Modified09/12/19
Administering AgencyW.S.S.C.
CategoryWSSC
SubCategoryWater Montgomery County
Planning AreaClarksburg and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision114210826000000000
Land13301330000000000
Site Improvements and Utilities00000000000
Construction4712461210000000000
Other2402400000000
Total Expenditures7208702418400000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
System Development Charge7208702418400000000
Total Funding Sources7208702418400000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY97
Appropriation FY 22 Request0
Last FY's Cost Estimate7332
Cumulative Appropriation13137
Expenditure / Encumbrances0
Unencumbered Balance13137