Phase 2 is ongoing in FY24-FY26 and will include full irrigation, additional parking, additional landscaping, loop trail, site amenities, and a second field.
project image
anchor

Phase

Under Construction

Status

Active
anchor
Budget Snapshot
$5.42M Total
Expenditures/Funding
$2.24M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Phase 2 design ongoing. Construction to begin in FY24.
anchor

Justification

The site selection and concept plan for this project was approved by the Montgomery County Planning Board on July 30, 2015. The 2012 Park Recreation and Open Space (PROS) plan estimated a need for four dedicated cricket fields in Montgomery County by the year 2022.
anchor

Fiscal Note

In FY22, $250k slipped from FY24 to FY25 for fiscal capacity.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. M-NCPPC asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
Budget Snapshot
$5.42M Total
Expenditures/Funding
$2.24M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP871746
Date Last Modified10/31/23
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaLower Seneca Basin
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision6802021952832305300000
Land00000000000
Site Improvements and Utilities473819927921954165030400000
Construction00000000000
Other00000000000
Total Expenditures541821949872237188035700000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds21361049737350350000000
PAYGO11451145000000000
Program Open Space213702501887153035700000
Total Funding Sources541821949872237188035700000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY16
Appropriation FY 26 Request0
Last FY's Cost Estimate5418
Cumulative Appropriation5418
Expenditure / Encumbrances2194
Unencumbered Balance3224