up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides design and construction of improvements to the hard surface trail system and connectors on parkland. Improvements may include, but are not limited to, pavements, site amenities (i.e. drinking fountains, benches, bike racks, bike repair stations, trailheads, etc.), safety improvements, skills facilities, rehabilitations, bridges and boardwalks, barriers, accessibility and drainage improvements, grading, site work, signage, etc. and are often combined with other projects.

anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$14.06M Total
Expenditures/Funding
$9M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost change due to the addition of FY29 and FY30 to this ongoing project, and additional funding required to match federal grants to renovate existing trails like Sligo Creek and Northwest Branch Trails with cost increases related to this new work.
anchor

Justification

Connectors, safety improvements, signage, and amenities increase trail usage for recreation and promote walking and biking as alternatives to vehicular transportation. In park user surveys, hiking and biking on trails is the most frequent recreation activity reported. Biking and walking paths top respondents' lists of desired facilities or greatest facility shortages. 2016 Countywide Park Trails Plan, 2017 Park, Recreation, and Open Space Plan.

anchor

Fiscal Note

Prior year partial capitalization of expenditures through FY16 totaled $11,542,000. FY15 Supplemental Appropriation for developer contribution of $900,000. FY15 transferred out $300,000 of GO bonds to Brookside Gardens Master Plan, #078702.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

State of Maryland, Montgomery County Department of Transportation, Washington Suburban Sanitary Commission and other utilities, Montgomery County Department of Environmental Protection, Maryland Department of Natural Resources, Trails: Hard Surface Renovation PDF 888754, Municipal Governments, Montgomery County Department of Permitting Services
Budget Snapshot
$14.06M Total
Expenditures/Funding
$9M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP768673
Date Last Modified04/19/24
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision333385949419809351652202202202200
Land00000000000
Site Improvements and Utilities1072524151290702033155857807807807800
Construction00000000000
Other00000000000
Total Expenditures14058327417849000425075010001000100010000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Contributions9008594100000000
Federal Aid35000035003500000000
G.O. Bonds965824151743550075075010001000100010000
Total Funding Sources14058327417849000425075010001000100010000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request4250
Year First AppropriationFY16
Appropriation FY 26 Request750
Last FY's Cost Estimate7508
Cumulative Appropriation5058
Expenditure / Encumbrances3740
Unencumbered Balance1318