Description

Projections indicate that enrollment at Silver Spring International Middle School is increasing and will exceed capacity throughout the six-year planning period. In addition to the enrollment growth, the gymnasiums and locker rooms are located in a separate building, down a steep hill, which impacts the accessibility and administration of the physical education program at the school. Also, the construction of the Purple Line will impact the school site and outdoor programmatic spaces that will need to be addressed. Therefore, the Board of Education's requested FY 2019-2024 CIP included funding for an addition at this school. An FY 2019 appropriation was approved to begin the planning for this project. An FY 2020 appropriation was approved for construction funds. This addition project not only will affect the middle school, but also the Sligo Creek Elementary School, since both are on the same site. After considering a number of factors including the cost and operational considerations for this project, the requested FY 2021-2026 CIP includes a one-year delay of this project to allow the school system and the school community an opportunity to explore additional options to address the capacity needs at both schools, as well as the programmatic needs at the middle school. This project, with the one-year delay, is scheduled to be completed September 2023. After careful consideration regarding the scope of this project, the fiscal challenges facing the county and state, and the substantial budget for the approved project, the Board of Education's Requested FY 2022 Capital Budget and Amendments to the FY 2021-2026 CIP includes a reduction of scope and cost of this addition project and to reevaluate the scope of the project to specifically address the programmatic and safety needs of the school as it relates to the location and administration of the physical education program, as well as the overall safety of the school community with the construction of the new Purple Line. With the approved change in scope, the completion date for this project was August 2024. In addition, the County Council approved the Board of Education's requested Amended CIP that included the reallocation of funds ($16 million) from this project to the Highland View Elementary School addition project. As part of the FY2023-2028 CIP, an additional $4.0 million from the county executive's Prevailing Wage and Built to Learn Act PDFs was included in this project to maximize state aid. Due to fiscal constraints, the County Council, in the adopted FY2023-2028 CIP, delayed this project one year. An FY2023 appropriation was approved for the additional funding for this project. An FY 2024 appropriation was approved for construction funds and an amendment to the FY 2023-2028 CIP was approved for additional funds due to the impact on the construction industry as a result of the Covid-19 pandemic. The scheduled completion date for this project is August 2025.
project image
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$28.14M Total
Expenditures/Funding
$15.15M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Fiscal Note

State Aid projected under the IAC Capital Improvement Program or the Built To Learn Act for school construction program.
anchor

Disclosures

MCPS asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Mandatory Referral - M-NCPPC, Department of Environmental Protection, Building Permits:, Code Review, Fire Marshall, Department of Transportation, Inspections, Sediment Control, Stormwater Management, WSSC Permits
Budget Snapshot
$28.14M Total
Expenditures/Funding
$15.15M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP651912
Date Last Modified12/03/23
Administering AgencyPublic Schools
CategoryMontgomery County Public Schools
SubCategoryIndividual Schools
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision24682468000000000
Land00000000000
Site Improvements and Utilities21890218900000000
Construction224985072941515410154500000000
Other985098500000000
Total Expenditures281402518104681515410154500000000
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds1966025181046866745027164700000
State Aid84800084805127335300000
Total Funding Sources281402518104681515410154500000000
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30
Maintenance438737373737373
Energy162272727272727
NET IMPACT600100100100100100100
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request0
Year First AppropriationFY19
Appropriation FY 26 Request0
Last FY's Cost Estimate28140
Cumulative Appropriation28140
Expenditure / Encumbrances0
Unencumbered Balance28140