up
Budget Year / Version:  
anchor
anchor
anchor

Description

This project provides for renovation or replacement of childcare facilities to ensure compliance with new laws pertaining to the Americans with Disabilities Act (ADA) and safety concerns.
The project addresses three major components:
1. Remedies ADA non-compliant features at childcare centers located in County buildings.
2. Provides for the design and construction of ADA compliant playgrounds at existing child care facilities while also incorporating other playground requirements included in COMAR 13A.16.01, National Association for the Education of Young Children Early Learning Standards and Accreditation Criteria, and the Maryland Program Accreditation Standards for Implementing Quality Childhood Programs.
3. Provides for replacement of modular facilities.
anchor

Phase

Planning Stage

Status

Active
anchor
Budget Snapshot
$27.99M Total
Expenditures/Funding
$26.24M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Project planning to take place in FY20-21. Design and construction will take place sequentially from FY21 through FY26.
anchor

Cost Change

Cost increase due to a preliminary planning analysis of facility needs.
anchor

Justification

This project is designed to bring childcare facilities and playgrounds into compliance with Federal ADA requirements.
anchor

Fiscal Note

All costs are preliminary. Actual costs will be determined after the planning phase is completed. The Department is required to provide notice and information to Council in writing 60 days before construction funding is obligated or spent. The notice must identify each project programmed for construction with the anticipated scope of work, cost estimates, and an expenditure schedule.
anchor

Coordination

Health and Human Services, Montgomery County Public Schools, Department of General Services, Office of Management and Budget, Maryland National Capital Park and Planning Commission, and childcare center service providers
Download & Explore
Budget Snapshot
$27.99M Total
Expenditures/Funding
$26.24M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP601901
Date Last Modified05/19/20
Administering AgencyGeneral Services
CategoryHealth and Human Services
SubCategoryHealth and Human Services
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision775348170260037446721063124081814660
Land00000000000
Site Improvements and Utilities00000000000
Construction1994300199431149208441114864355141840
Other298002983437296842880
Total Expenditures27994481702262441927279352036172441157380
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds27994481702262441927279352036172441157380
Total Funding Sources27994481702262441927279352036172441157380
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request1927
Year First AppropriationFY19
Appropriation FY 22 Request2793
Last FY's Cost Estimate11750
Cumulative Appropriation1750
Expenditure / Encumbrances48
Unencumbered Balance1702