Description

This project provides for the investigation and analysis of various storm drainage assistance requests initiated by private citizens and public agencies. These requests are related to the design, construction, and operation of public drainage facilities where flooding and erosion occur. This project includes expenditures for the preliminary and final design and land acquisition for storm drain projects prior to inclusion in the Storm Drain General project, or as a stand-alone project in the Capital Improvements Program (CIP). Prior to its inclusion in the CIP, the Department of Transportation (DOT) will conduct a feasibility study to determine the general and specific features required for the project. Candidate projects currently are evaluated from the Drainage Assistance Request list. As part of the facility planning process, DOT considers citizen and public agency requests and undertakes a comprehensive analysis of storm drainage issues and problems being experienced in the County. This analysis is used to select areas where a comprehensive long-term plan for the remediation of a problem may be required. No construction activities are performed in this project. When a design is 35 percent complete, an evaluation is performed to determine if right-of-way is needed. Based on the need for right-of-way, the project may proceed to final design and the preparation of right-of-way plats under this project. The cost of right-of-way acquisition will be charged to the Advanced Land Acquisition Revolving Fund (ALARF). When designs are complete, projects with a construction cost under $500,000 will be constructed in the Storm Drain General project. Projects with a construction cost over $500,000 will be constructed in stand-alone projects.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$8.28M Total
Expenditures/Funding
$1.92M 6 Year Total
Expenditures/Funding
anchor

Capacity

Projects will be designed to accommodate the ten year storm frequency interval.
anchor

Cost Change

Increase due to the addition of FY25 & FY26 to this on-going level of effort project. Increase of $30,000 annually to expedite the readiness of projects into construction.
anchor

Justification

Evaluation, justification, and cost-benefit analysis are completed by DOT as necessary. In the case of participation projects, drainage studies and preliminary plans will be prepared by the requestor's engineer and reviewed by DOT. Traffic signals, streetlights, crosswalks, bus stops, ADA ramps, bikeways and other pertinent issues are being considered in the design of the project to ensure pedestrian safety.
anchor

Other

Before being added as a sub-project, concept studies are evaluated based on the following factors: public safety; damage to private property; frequency of event; damage to public right-of-way; environmental factors such as erosion, general public benefit, availability of right-of-way; and 5:1 cost benefit damage prevented ratio. In the case of public safety or severe damage to private property, the 5:1 cost benefit damage prevented ratio can be waived. Drainage assistance requests are evaluated on a continuing basis in response to public requests. DOT maintains a database of complaints. Recent construction projects completed include: Crown Street, Grafton Street, Lanier Drive, Ogden Court, Ashburton Lane, Mintwood Street, Woodland Drive, Stable Lane and Charred Oak Drive. Candidate Projects for FY21 and FY22: Tranford Road, Windmill Lane, and Conway Drive.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Expenditures will continue indefinitely.
anchor

Coordination

Montgomery County Department of Environmental Protection, Maryland-National Capital Park and Planning Commission, Maryland Department of the Environment, United States Army Corps of Engineers, Montgomery County Department of Permitting Services, Utility Companies, and Sidewalk Program - Minor Projects (CIP No. 506747).
Download & Explore
Budget Snapshot
$8.28M Total
Expenditures/Funding
$1.92M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP508180
Date Last Modified03/25/20
Administering AgencyTransportation
CategoryConservation of Natural Resources
SubCategoryStorm Drains
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision8097578838919203203203203203203200
Land142142000000000
Site Improvements and Utilities00000000000
Construction4040000000000
Other55000000000
Total Expenditures8284597538919203203203203203203200
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Current Revenue: General41034103000000000
Current Revenue: Water Quality Protection4080177138919203203203203203203200
G.O. Bonds101101000000000
Total Funding Sources8284597538919203203203203203203200
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request320
Year First AppropriationFY81
Appropriation FY 22 Request320
Last FY's Cost Estimate7524
Cumulative Appropriation6364
Expenditure / Encumbrances6035
Unencumbered Balance329