Description

This pedestrian access improvement program provides sidewalks on County-owned roads and some State-maintained roadways. Some funds from this project will go to support the Renew Montgomery program. The Department of Transportation maintains an official list of all outstanding sidewalk requests. Future projects are evaluated and selected from this list, which is continually updated with new requests. In addition, projects identified by the Citizens' Advisory Boards are placed on the list. One aspect of this project will focus on improving pedestrian walkability by creating a safer walking environment, utilizing selected engineering technologies, and ensuring Americans with Disabilities Act of 1990 (ADA) compliance.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$52.28M Total
Expenditures/Funding
$23.39M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost change is due to inflation and the addition of FY29 and FY30.
anchor

Justification

In addition to connecting existing sidewalks, these projects increase pedestrian safety and facilitate walking to: Metrorail stations, bus stops, shopping and medical centers, employment, recreational, and school sites. This program also complements and augments the bikeways that are included in road projects.
anchor

Other

Projects originate from requests by residents, civic associations, and public agencies. Requests are evaluated and scheduled using sidewalk prioritization procedures. The project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County Roadways to zero by 2030.
DOT is reviewing the GIS-based prioritization tool which will help evaluate the sidewalk requests based on safety, trip generators, and equity data.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project. Expenditures will continue indefinitely. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Renew Montgomery Program, Maryland-National Capital Park and Planning Commission, Maryland DOT State Highway Administration, Montgomery County Public Schools, Washington Metropolitan Area Transit Authority, Sidewalk and Infrastructure Revitalization , Maryland Mass Transit Administration, Montgomery County Pedestrian Safety Advisory Committee, Commission on People with Disabilities
Budget Snapshot
$52.28M Total
Expenditures/Funding
$23.39M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP506747
Date Last Modified01/08/24
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
Planning, Design and Supervision152948530180349617618408408408408400
Land2550231062342525464646460
Site Improvements and Utilities45736013841414141414140
Construction33975136152251181092440375628082919303431520
Other44000000000
Total Expenditures52280248194073233883240463537083819393440520
FUNDING (000s)
Funding SourceTotalThru FY23Est FY24Total 6 YearsFY 25FY 26FY 27FY 28FY 29FY 30Beyond 6 Years
G.O. Bonds49940224794073233883240463537083819393440520
Recordation Tax Premium (MCG)22642264000000000
State Aid7676000000000
Total Funding Sources52280248194073233883240463537083819393440520
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 25 Request3240
Year First AppropriationFY67
Appropriation FY 26 Request4635
Last FY's Cost Estimate43592
Cumulative Appropriation28892
Expenditure / Encumbrances25978
Unencumbered Balance2914