Description

This project funds the design and construction of pedestrian and bicycle improvements to Flash stations along the US 29 corridor. First and last mile connections to Flash BRT stations along US 29 were identified as part of the US 29 Mobility and Reliability Study effort. These sub projects would expand and improve the existing pedestrian and bicycle network by filling gaps and upgrading existing facilities. Potential projects could include new and upgraded crosswalks and pedestrian signals, new and upgraded curb ramps, new and upgraded sidewalks, and new and upgraded bicycle facilities. Projects that improve ADA access will be prioritized. Added State Aid will support improvements north of Randolph Road.
anchor

Phase

Preliminary Design Stage

Status

Active
anchor
Budget Snapshot
$5.5M Total
Expenditures/Funding
$5.5M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Design and construction for projects north of Randolph road would start in FY23 and FY24. Design and construction for projects south of Randolph Road would begin in FY25 and continue into future fiscal years.
anchor

Justification

These projects will complement the initial investment the county and federal government made in the US 29 Flash service by expanding and improving access for pedestrians and cyclists to the stations. The projects will also improve pedestrian and bicyclist mobility and safety. Projects will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County roadways. Improving access to US 29 Flash supports master plan efforts to increase the number of persons traveling by bike, on foot, and via transit. This is in line with the County's Climate Action Plan goals for reducing greenhouse gas emissions. The project supports the following countywide vision goals: Safe Neighborhoods, Easier Commutes, and a Growing Economy. Approved land use plans in the corridor recommend the implementation of transit lanes and new pedestrian and bicycle infrastructure along with US 29 Flash. The project is consistent with the Countywide Transit Corridors Functional Master Plan and County Bicycle Master Plan.
anchor

Fiscal Note

Construction cost estimates are based on facility planning conceptual cost estimates completed in FY21 of $95 million. Construction costs will be updated as design progresses. State Aid reflects state grants for capital projects in Montgomery County programmed during the 2022 State General Assembly Session. It is intended to address first- and last-mile access for stations north of Randolph Road.
anchor

Disclosures

A pedestrian impact analysis will be performed during design or is in progress. The County Executive asserts that this project conforms to the requirement of relevant local plans, as required by the Maryland Economic Growth, Resource Protection and Planning Act.
anchor

Coordination

Maryland-National Capital Park and Planning Commission (M-NCPPC), Maryland DOT State Highway Administration & Maryland Transit Administration, Utility Companies, Department of Environmental Protection, Department of Permitting Services, Washington Gas, Pepco, Baltimore Gas & Electric (BG&E), Comcast, Verizon, Maryland Department of Natural Resources, Montgomery County Pedestrian Safety Advisory Committee, Commission on People with Disabilities, Citizen Advisory Boards, US 29 BRT Corridor Advisory Committee, Neighborhood and Civic Associations, Montgomery County Bicycle Action Group, Washington Area Bicycle Association, and Washington Metropolitan Area Transit Authority (WMATA).

Budget Snapshot
$5.5M Total
Expenditures/Funding
$5.5M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP502304
Date Last Modified05/20/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryPedestrian Facilities/Bikeways
Planning AreaSilver Spring and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision125000125050001251252502500
Land00000000000
Site Improvements and Utilities00000000000
Construction425000425050015003753757507500
Other00000000000
Total Expenditures550000550010001500500500100010000
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
G.O. Bonds300000300000500500100010000
State Aid25000025001000150000000
Total Funding Sources550000550010001500500500100010000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request2500
Year First AppropriationFY23
Appropriation FY 24 Request0
Last FY's Cost Estimate5500
Cumulative Appropriation2500
Expenditure / Encumbrances0
Unencumbered Balance2500