Description

This program will provide for the replacement of failed storm drain pipes and culverts. The County's storm drain infrastructure is aging and many of the metal pipe culverts installed from 1960 through the 1990's have reached the end of their service life. An asset inventory with condition assessments has been developed to better forecast future replacement needs. Going forward, funding will be programmed for both systematic and emergency replacement of these pipes and culverts. Program scope includes: storm water pipe and culvert replacement of both metal and concrete less than six (6) feet in roadway longitudinal length; headwalls, end sections, replacement, or extension of culverts to assure positive flow of stormwater and channeling of stormwater into existing ditch lines or structures. Repairs also include roadside pipe and culvert end treatment safety improvements to eliminate safety hazards. This project will not make major changes to the location or size of existing storm drainage facilities. Structures greater than six-feet-roadway-longitudinal length are repaired under the Bridge Renovation Program, (CIP No. 509753).
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$20M Total
Expenditures/Funding
$9.7M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase due to the addition of FY25-26 to this ongoing level of effort project. FY22-26 increase of $500,000 per year to increase the level of effort and to provide flexibility to deal with emergencies.
anchor

Justification

This program will address emergency pipe replacements of aging metal and concrete pipes that have reached the end-of-their-service life. The result of these pipe failures has been deep depressions, sinkholes, sediment build-up, open pipe joints, and metal pipe inverts to an unacceptable levels. Existing storm drain conditions are extremely poor. Repairs are needed to improve safety and reduce the potential for hazards and associated public inconvenience. Failure of a storm drain pipe will precipitate emergency repairs at much higher prices. Furthermore, this program provided funding towards developing an asset inventory of the storm drain system including pipe and culvert conditions that helps forecast future funding requirements.
anchor

Fiscal Note

In FY19, Water Quality Protection Bonds were replaced with long-term financing based on the Maryland Water Quality Revolving Loan Fund (WQRLF) to finance water quality improvement projects with low-interest loans which are less costly than bond sales.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Washington Suburban Sanitary Commission, Washington Gas Company, Montgomery County Department of Permitting Services, Pepco, Cable TV, Verizon, Montgomery County Public Schools, Regional Service Centers, Community Association's, Commission on People With Disabilities, Maryland Department of Environment, Montgomery County Department of Environmental Protection, and United States Army Corps of Engineers.
Download & Explore
Budget Snapshot
$20M Total
Expenditures/Funding
$9.7M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP501470
Date Last Modified05/17/20
Administering AgencyTransportation
CategoryConservation of Natural Resources
SubCategoryStorm Drains
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision3000120034514551802552552552552550
Land00000000000
Site Improvements and Utilities00000000000
Construction16998782293182451020144514451445144514450
Other22000000000
Total Expenditures200009024127697001200170017001700170017000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Current Revenue: Water Quality Protection40004000000000000
G.O. Bonds15001500000000000
Long-Term Financing121001124127697001200170017001700170017000
Water Quality Protection Bonds24002400000000000
Total Funding Sources200009024127697001200170017001700170017000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request1200
Year First AppropriationFY14
Appropriation FY 22 Request1700
Last FY's Cost Estimate15100
Cumulative Appropriation10300
Expenditure / Encumbrances9038