Description

This project provides for the evaluation and enhancement of streetlighting within and around Central Business Districts (CBD) and town centers where current lighting does not meet minimum Illuminating Engineering Society of North America (IESNA) standards. This project will fill in streetlighting; standardize streetlighting types; and replace sodium vapor lights with light-emitting diode (LED) lights.
anchor

Phase

Ongoing

Status

Active
anchor
Budget Snapshot
$5.93M Total
Expenditures/Funding
$1.5M 6 Year Total
Expenditures/Funding
anchor

Cost Change

Cost increase due to the addition of FY27 and FY28 to this ongoing project.
anchor

Justification

This project is needed to provide visibility and safety improvements in areas where there is a high concentration of pedestrians, bicyclists, and vehicles. Streetlighting to promote pedestrian safety is one of the items requested each year by the Citizens' Advisory Boards (CABs).
anchor

Other

Streetlighting in CBD's and town centers will also support the Montgomery County Planning Board (MCPB) priorities for County-wide pedestrian safety improvements and area specific lighting enhancements. Completed projects include: Long Branch (commercial area) - completed in FY10; Wheaton CBD - completed in FY11; Langley Park - completed in FY12; Odenthal Avenue - completed in FY13; Damascus Town Center - completed in FY14; Glenmont Metro Area - completed in FY15; Olney Town Center - completed in FY17; Bethesda is currently underway; Silver Spring scheduled next. This project will help the County achieve its Vision Zero goals to reduce deaths and serious injuries on County roadways to zero by 2030.
anchor

Disclosures

Expenditures will continue indefinitely.
anchor

Coordination

Potomac Electric Power Company, Baltimore Gas and Electric Company, Potomac Edison, Montgomery County Police Department, Community Associations, Urban Districts, Citizens' Advisory Boards, and Maryland-National Capital Park and Planning Commission.
Budget Snapshot
$5.93M Total
Expenditures/Funding
$1.5M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP500512
Date Last Modified10/25/22
Administering AgencyTransportation
CategoryTransportation
SubCategoryTraffic Improvements
Planning AreaCountywide
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Planning, Design and Supervision1348104803005050505050500
Land00000000000
Site Improvements and Utilities4371301815312002002002002002002000
Construction00000000000
Other211211000000000
Total Expenditures5930427715315002502502502502502500
FUNDING (000s)
Funding SourceTotalThru FY22Rem FY22Total 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28Beyond 6 Years
Current Revenue: Urban District Bethesda435435000000000
G.O. Bonds5495384215315002502502502502502500
Total Funding Sources5930427715315002502502502502502500
OPERATING BUDGET IMPACT ($000s)
Impact TypeTotal 6 YearsFY 23FY 24FY 25FY 26FY 27FY 28
Maintenance9091215181818
Energy46568999
NET IMPACT136141823272727
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 23 Request250
Year First AppropriationFY05
Appropriation FY 24 Request250
Last FY's Cost Estimate5930
Cumulative Appropriation4680
Expenditure / Encumbrances4433
Unencumbered Balance247