Description

This project provides for the design and construction of pedestrian improvements to complete unfinished streetscapes along approximately 2,670 feet of Central Business District (CBD) streets in Bethesda as identified in the Bethesda CBD Sector Plan. This includes 475 feet along Woodmont Avenue between Old Georgetown Road and Cheltenham Drive; 1,825 feet along Wisconsin Avenue between Cheltenham Drive and the northern end of the CBD; and 370 feet along East-West Highway between Waverly Street and Pearl Street. It is intended to fill the gaps between private development projects which have been constructed or are approved in the CBD. The design elements include the replacement and widening (where possible) of sidewalks, new vehicular and pedestrian lighting, street trees, street furniture, and roadway signs. This project addresses streetscape improvements only and does not assume the undergrounding of utilities.
anchor

Phase

Preliminary Design Stage

Status

Closeout
anchor
Budget Snapshot
$0.42M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Cost Change

Reduction due to project being closed out. Developers have been covering these activities and are expected to going forward.
anchor

Justification

Bethesda Downtown Sector Plan, approved and adopted May 2017; and Bethesda Streetscape Plan Standards, updated April 1992.
anchor

Other

Since the current scope was approved in FY13, developers have been required to construct portions of the work along East-West Highway, Woodmont Avenue and Wisconsin Avenue. This project will study potential replacement segments that can be completed with the savings derived from the developer-built segments. Potential candidate segments on Norfolk Avenue, Woodmont Avenue, and Cordell Avenue will be considered. Coordination with Pepco revealed that the installation of aesthetic coverings on existing utility poles is not technically feasible.
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Maryland-National Capital Park and Planning Commission, Montgomery County Public Schools, Department of Permitting Services, Maryland State Highway Administration, Utility Companies, Bethesda-Chevy Chase Regional Services Center
Download & Explore
Budget Snapshot
$0.42M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor
Project Details
Project NumberP500102
Date Last Modified05/16/20
Administering AgencyTransportation
CategoryTransportation
SubCategoryRoads
Planning AreaBethesda-Chevy Chase and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision416416000000000
Land00000000000
Site Improvements and Utilities00000000000
Construction00000000000
Other00000000000
Total Expenditures416416000000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds416416000000000
Total Funding Sources416416000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY01
Appropriation FY 22 Request0
Last FY's Cost Estimate5721
Cumulative Appropriation1502
Expenditure / Encumbrances434
Unencumbered Balance1068