Description

Battery Lane Urban Park is a 1.9-acre existing park located at the edge of the Bethesda Central Business District. The approved facility plan includes the renovation of the following amenities in the park: tennis court, enlarged playground, walking path, basketball court, improved entryway, lighting, seating, drinking fountain, landscaping, and bike racks. The plan provides for better maintenance access. Due to fiscal constraints and changes in recommendations for this park from the staff draft of the Bethesda Downtown Plan, the funding for the project has been reduced to only renovate the playground, which is well beyond its lifecycle for replacement. Redevelopment of the entire park is on hold.
project image
anchor

Phase

Under Construction

Status

Closeout
anchor
Budget Snapshot
$0.19M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Justification

The Woodmont Triangle Amendment to the Sector Plan for the Bethesda CBD (2006) lists Battery Lane Urban Park as a priority public amenity and facility. The park is one of the two major green spaces within the Woodmont Triangle area. The Facility Plan was approved by the Planning Board on July 30, 2009.
anchor

Fiscal Note

FY14 Supplemental Appr. of $1.93m ($860k in State Aid, $1.07m GO Bonds). Funds for this project were originally programmed through Bikeway Program-Minor Projects (CIP #507596).
anchor

Disclosures

A pedestrian impact analysis has been completed for this project.
anchor

Coordination

Developer, Montgomery County Planning Department
Budget Snapshot
$0.19M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP118701
Date Last Modified05/18/20
Administering AgencyM-NCPPC
CategoryM-NCPPC
SubCategoryDevelopment
Planning AreaBethesda-Chevy Chase and Vicinity
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision6060000000000
Land00000000000
Site Improvements and Utilities130130000000000
Construction00000000000
Other00000000000
Total Expenditures190190000000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
M-NCPPC Bonds190190000000000
Total Funding Sources190190000000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY17
Appropriation FY 22 Request0
Last FY's Cost Estimate190
Cumulative Appropriation190
Expenditure / Encumbrances190
Unencumbered Balance0