Description

This project provides funding for major building infrastructure improvements to Macklin Tower including replacement of major mechanical, electrical, and plumbing systems and equipment; upgrade/replacement of life safety systems (fire alarm, emergency generator and sprinkler systems); upgrade/replacement of building elevators; and building access upgrades. The College completed a facilities condition assessment of the building in August 2002 that evaluated all building systems and related equipment and identified major repair and/or replacement requirements.
project image
anchor

Phase

Under Construction

Status

Closeout
anchor
Budget Snapshot
$10.6M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
anchor

Location

anchor

Estimated Schedule

Project construction was completed Spring 2019.
anchor

Justification

Macklin Tower was constructed in 1971 and this forty-seven year old facility is experiencing a progressive deterioration of building systems and major pieces of building equipment. It has now reached the point that addressing the problem of a deteriorating building infrastructure is beyond the scope of a maintenance effort and that building repairs are no longer adequate or cost effective. Key components of the HVAC, mechanical and electrical systems are outdated, energy inefficient, and costly to continue to repair. The refurbishment and/or replacement of major building systems and related equipment will significantly extend the useful life of the building and correct safety and environmental problems. This project is coordinated with the College's FY02 supplemental appropriation request to the PLAR project (CIP #P926659) to correct significant water and air infiltration problems with a failing exterior curtain wall framing system and a deteriorating sealant used on all of the building's windows. The College completed a building condition assessment in 2002 that provides a detailed evaluation of building deficiencies and initial cost estimates for major repairs, equipment replacements, and related improvements. Schematic Design for Curtain Wall Remediation - Macklin Tower (5/25/01) and Curtain Wall and Building Envelope Investigation - Macklin Tower (3/16/01). Montgomery College 2025 Strategic Plan, Collegewide Facilities Condition Assessment (12/13) and Collegewide Facilities Master Plan Update (6/18).
anchor

Other

Funding Source: G.O. Bonds. The following fund transfer has been made from this project: $400,000 to the Takoma Park Campus Expansion Project (# 996662) (BOT Resol. # 07-01-005, 01/16/07).
anchor

Fiscal Note

In December 2001, the County Council approved an FY02 supplemental capital budget appropriation of $2,075,000 to the PLAR project (CIP #P926659) to replace the building's exterior curtain wall to correct problems associated with a failing exterior curtain wall framing system and a deteriorating window sealant. The exterior curtain wall replacement was completed in spring 2003. An engineering evaluation of the building's fire alarm system and emergency generator was completed in August 2002 and a design/build replacement of this system and equipment was completed in summer 2003 for the tower. Mechanical and electrical equipment upgrades of floors 2-6 in the tower have been completed (2004/2005). The current focus is mechanical, electrical and plumbing upgrades for the ground floor.
anchor

Coordination

Energy Conservation: College (CIP No. P816611), Planned Lifecycle Asset Replacement: College (CIP No. P926659), Roof Replacement: College (CIP No. P876664), Collegewide Library Renovations (CIP No. P661901)
Download & Explore
Budget Snapshot
$10.6M Total
Expenditures/Funding
$0M 6 Year Total
Expenditures/Funding
project image
anchor
Project Details
Project NumberP036603
Date Last Modified12/17/19
Administering AgencyMontgomery College
CategoryMontgomery College
SubCategoryHigher Education
Planning AreaRockville
anchor
Total Expenditures by Cost Element (000s)
anchor
Total Funding by Source (000s)
EXPENDITURES (000s)
Cost ElementsTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
Planning, Design and Supervision159115504100000000
Land00000000000
Site Improvements and Utilities00000000000
Construction9013888113200000000
Other00000000000
Total Expenditures106041043117300000000
FUNDING (000s)
Funding SourceTotalThru FY19Est FY20Total 6 YearsFY 21FY 22FY 23FY 24FY 25FY 26Beyond 6 Years
G.O. Bonds106041043117300000000
Total Funding Sources106041043117300000000
APPROPRIATION AND EXPENDITURE DATA ($000s)
Appropriation FY 21 Request0
Year First AppropriationFY03
Appropriation FY 22 Request0
Last FY's Cost Estimate10604
Cumulative Appropriation10604
Expenditure / Encumbrances10573
Unencumbered Balance31